Foundations, framing and structure (Part 9)

Excavation, dampproofing, drainage, footings and foundations, floors-on-ground, columns, crawl spaces, roof spaces, masonry, chimneys, fireplaces, wood-frame and steel stud construction.

chapters in this guide
12 of 15
chapters in this guide
to read
7 min
to read
code articles cited
48
code articles cited

Last updated

Values this chapter turns on

footing width added per storey of veneer
65 mm
footing width added per storey of veneer
roof vent area to insulated ceiling area
1/300
roof vent area to insulated ceiling area
maximum hole size in a joist
1/4 depth
maximum hole size in a joist
max notch depth, top of joist near bearing
1/3 depth
max notch depth, top of joist near bearing

This chapter covers the structural parts of Part 9, from excavation to steel studs. These Sections apply the same way to a house, a small office or a small apartment building. Most questions are number lookups, so know which article holds which number and read the tables carefully.

Excavation, dampproofing, soil gas and drainage

Foundations must bear on undisturbed soil OBC Div. B 9.12.2.1.OBC Div. B 9.12.2.1. Excavation to Undisturbed Soil(1) Excavations for foundations shall extend to undisturbed soil.. The minimum depth comes from Table 9.12.2.2, which you read by soil type, then by whether the foundation encloses heated space, then by soil drainage OBC Div. B 9.12.2.2.OBC Div. B 9.12.2.2. Minimum Depth of Foundations(1) Except as provided in Sentences (4) to (7), the minimum depth of foundations below finished ground level shall conform to Table 9.12.2.2. (2) Where a foundation is insulated in a manner that will reduce the heat flow to the soil beneath the footings, the foundation depth shall conform to that required for…. Rock has no depth limit. Clay and poorly defined soils need 1.2 m. Under a foundation with no heated space, silt, and coarse soil with poor drainage, need depth below frost penetration. A foundation insulated so that heat does not reach the soil under the footings is treated as having no heated space. Small accessory buildings and low decks that meet every listed limit are exempt.

Backfill within 600 mm of the wall must be free of debris and of boulders over 250 mm OBC Div. B 9.12.3.3.OBC Div. B 9.12.3.3. Deleterious Debris and Boulders(1) Backfill that is within 600 mm of the foundation shall be free of deleterious debris and boulders larger than 250 mm diam. (See Note A-9.12.3.3.(1)) (2) Except as permitted in Sentence (3), backfill shall not contain pyritic material or material that is susceptible to ice lensing in concentrations that will damage…. It must also be graded so water does not drain toward the foundation once it settles OBC Div. B 9.12.3.2.OBC Div. B 9.12.3.2. Grading of Backfill(1) Backfill shall be graded to prevent drainage towards the foundation after settling..

Foundation walls below ground are dampproofed where outside ground is higher than inside ground, unless they are waterproofed. Floors-on-ground are dampproofed too, except garage floors, unenclosed floors and floors over the granular fill of 9.16.2.1 OBC Div. B 9.13.2.1.OBC Div. B 9.13.2.1. Required Dampproofing(1) Except as provided in Sentence (4) and Article 9.13.3.1., where the exterior finished ground level is at a higher elevation than the ground level inside the foundation walls, exterior surfaces of foundation walls below ground level shall be dampproofed. (2) Except as provided in Sentence (3) and Article 9.13.3.1.…. Waterproofing is needed instead where there is hydrostatic pressure OBC Div. B 9.13.3.1.OBC Div. B 9.13.3.1. Required Waterproofing(1) Where hydrostatic pressure occurs, waterproofing is required for assemblies separating interior space from the ground to prevent the ingress of water into building assemblies and interior spaces. (2) Waterproofing is required for roofs of underground structures to prevent the ingress of water into building….

Assemblies in contact with the ground must resist soil gas leakage, except in garages and unenclosed spaces OBC Div. B 9.13.4.2.OBC Div. B 9.13.4.2. Protection from Soil Gas Ingress(1) Except as provided in Sentence (1.1), all wall, roof and floor assemblies in contact with the ground shall be constructed to resist the leakage of soil gas from the ground into the building in accordance with Subsection 9.25.3. or MMAH Supplementary Standard SB-9, "Requirements for Soil Gas Control." (1.1)…. Any building containing a residential occupancy, not just a house, needs a radon rough-in, unless the space under the air barrier is built to be accessible for a future depressurization system. One accepted rough-in is clean granular fill under the slab with a pipe of at least 100 mm diameter ending near the centre of the floor, capped airtight and labelled OBC Div. B 9.13.4.3.OBC Div. B 9.13.4.3. Providing for the Rough-in for a Subfloor Depressurization System(1) Floors-on-ground shall be provided with a rough-in for subfloor depressurization consisting of (a) a gas-permeable layer, an inlet and an outlet as described in Sentence (2), or (b) clean granular material and a pipe as described in Sentence (3). (2) The rough-in referred to in Clause (1)(a) shall include (a) a…. Other occupancies may use that rough-in or follow Parts 5 and 6.

Drainage item Key number Article
Foundation drain tile or pipe at least 100 mm diameter 9.14.3.2
Stone cover over tile at least 150 mm 9.14.3.3
Sump pit at least 750 mm deep and 0.25 m2 9.14.5.2

Foundation drains discharge to a sewer, drainage ditch or dry well OBC Div. B 9.14.5.1.OBC Div. B 9.14.5.1. Drainage Disposal(1) Foundation drains shall drain to a sewer, drainage ditch or dry well..

Practice this topic

Footings, foundations and floors-on-ground

The Part 9 footing tables only work inside limits: soil bearing of at least 75 kPa OBC Div. B 9.15.1.1.OBC Div. B 9.15.1.1. General(1) Except as provided in Articles 9.15.1.2. and 9.15.1.3., this Section applies to (a) concrete or unit masonry foundation walls and concrete footings not subject to surcharge (i) on stable soils with an allowable bearing pressure of 75 kPa or greater, and (ii) for buildings of wood-frame or masonry construction, (b)…, joist spans not over 4.9 m and floor live load not over 2.4 kPa OBC Div. B 9.15.3.3.OBC Div. B 9.15.3.3. Application of Footing Width and Area Requirements(1) Except as provided in Sentence 9.15.3.4.(2), the minimum footing width or area requirements provided in Articles 9.15.3.4. to 9.15.3.7. shall apply to footings, where (a) the footings support (i) foundation walls of masonry, concrete, or flat insulating concrete form walls, (ii) above ground walls of masonry, flat…. Outside those, design to Section 4.2.

Table 9.15.3.4 gives a base width by the number of floors supported OBC Div. B 9.15.3.4.OBC Div. B 9.15.3.4. Basic Footing Widths and Areas(1) Except as provided in Sentences (2) and (3) and in Articles 9.15.3.5. to 9.15.3.7., the minimum footing width or area shall comply with Table 9.15.3.4. (2) Where the supported joist span exceeds 4.9 m in buildings with light wood-frame walls, floors and roofs, strip footing widths shall be determined according to…. You then add for heavy walls above OBC Div. B 9.15.3.5.OBC Div. B 9.15.3.5. Adjustments to Footing Widths for Exterior Walls(1) The strip footing widths for exterior walls shown in Table 9.15.3.4. shall be increased by (a) 65 mm for each storey of masonry veneer over wood-frame construction supported by the foundation wall, (b) 130 mm for each storey of masonry construction supported by the foundation wall, and (c) 150 mm for each storey…:

Exterior wall type above, per storey Add to table width
Masonry veneer over wood frame 65 mm
Solid masonry 130 mm
Flat ICF wall 150 mm

Step footings may rise no more than 600 mm per step, with at least 600 mm of run between risers OBC Div. B 9.15.3.9.OBC Div. B 9.15.3.9. Step Footings(1) Where step footings are used, (a) the vertical rise between horizontal portions shall not exceed 600 mm, and (b) the horizontal distance between risers shall be not less than 600 mm.. Exterior foundation walls must extend at least 150 mm above finished ground OBC Div. B 9.15.4.6.OBC Div. B 9.15.4.6. Extension Above Ground Level(1) Exterior foundation walls shall extend not less than 150 mm above finished ground level.. Wall thickness versus backfill height comes from Table 9.15.4.2.-A. Read the row by wall thickness, then the column by whether the wall is laterally supported at the top and how tall it is OBC Div. B 9.15.4.2.OBC Div. B 9.15.4.2. Foundation Wall Thickness and Required Lateral Support(1) Except as required in Sentence (2), the thickness of foundation walls made of unreinforced concrete block, concrete core in flat wall insulating concrete forms or solid concrete and subject to lateral earth pressure shall conform to Table 9.15.4.2.-A for walls not exceeding 3.0 m in unsupported height. (2) The…. Lateral support at the top is defined in OBC Div. B 9.15.4.3.OBC Div. B 9.15.4.3. Foundation Walls Considered to be Laterally Supported at the Top(1) Sentences (2) to (4) pertain to lateral support for walls described in Sentence 9.15.4.2.(1). (2) Foundation walls shall be considered to be laterally supported at the top if (a) such walls support a solid masonry superstructure or flat insulating concrete form wall, (b) the floor joists are embedded in the top of….

Floors-on-ground get at least 100 mm of coarse clean granular fill, except in garages, carports and accessory buildings OBC Div. B 9.16.2.1.OBC Div. B 9.16.2.1. Required Installation of Granular Fill(1) Except as provided in Sentence (2), not less than 100 mm of coarse clean granular material containing not more than 10% of material that will pass a 4 mm sieve shall be placed beneath floors-on-ground. (See also Subsection 9.13.4. and Note A-9.13.4.) (2) Granular material need not be installed under (a) slabs in…. Concrete slabs are at least 75 mm thick, not counting any topping OBC Div. B 9.16.4.3.OBC Div. B 9.16.4.3. Thickness(1) Concrete slabs shall be not less than 75 mm thick exclusive of concrete topping. (See Note A-9.16.4.3.(1)).

Practice this topic

Columns, crawl spaces and roof spaces

Columns sit centred on a footing OBC Div. B 9.17.2.1.OBC Div. B 9.17.2.1. Location(1) Columns shall be centrally located on a footing conforming to Section 9.15.. A steel pipe column needs at least 73 mm outside diameter and 4.76 mm wall unless capacity is shown OBC Div. B 9.17.3.1.OBC Div. B 9.17.3.1. Size and Thickness(1) Except as permitted in Sentence (2), steel pipe columns shall have an outside diameter of not less than 73 mm and a wall thickness of not less than 4.76 mm. (2) Columns of sizes other than as specified in Sentence (1) are permitted to be used where the loadbearing capacities are shown to be adequate.. Wood columns are at least 140 mm by 140 mm (or 184 mm round) and never narrower than the member they carry OBC Div. B 9.17.4.1.OBC Div. B 9.17.4.1. Column Sizes(1) The width or diameter of a wood column shall be not less than the width of the supported member. (2) Except as provided in Article 9.35.4.2., columns shall be not less than 184 mm for round columns and 140 mm by 140 mm for rectangular columns, unless calculations are provided to show that lesser sizes are adequate..

A crawl space counts as heated if it is a warm air plenum, has unsealed and uninsulated heating ducts or pipes, or is not separated from heated space OBC Div. B 9.18.1.3.OBC Div. B 9.18.1.3. Heated and Unheated Crawl Spaces(1) Crawl spaces shall be considered to be heated where the space (a) is used as a warm air plenum, (b) contains heating ducts or heating pipes that are not sealed and insulated to minimize heat loss to the space, or (c) is not separated from heated space in accordance with Section 9.25. (2) Heating of heated crawl…. Access openings are 500 mm by 700 mm for one dwelling unit and 550 mm by 900 mm for every other crawl space OBC Div. B 9.18.2.1.OBC Div. B 9.18.2.1. Access Openings(1) An access opening of not less than 500 mm by 700 mm shall be provided to each crawl space where the crawl space serves a single dwelling unit, and not less than 550 mm by 900 mm for other crawl spaces. (2) Access openings shall be fitted with a door or hatch, except when the crawl space is heated and the access…. Unheated crawl spaces vented naturally need 0.1 m2 of vent for each 50 m2 of floor OBC Div. B 9.18.3.1.OBC Div. B 9.18.3.1. Ventilation of Unheated Crawl Spaces(1) Unheated crawl spaces shall be ventilated by natural or mechanical means. (2) Where an unheated crawl space is ventilated by natural means, ventilation shall be provided to the outside air by not less than 0.1 m² of unobstructed vent area for every 50 m² of floor area. (3) Vents shall be (a) uniformly distributed… and a ground cover such as 0.10 mm polyethylene lapped 100 mm OBC Div. B 9.18.6.1.OBC Div. B 9.18.6.1. Ground Cover in Unheated Crawl Spaces(1) Where a crawl space is unheated, a ground cover shall be provided consisting of not less than (a) 50 mm of asphalt, (b) 100 mm of 15 MPa Portland cement concrete, (c) Type S roll roofing, or (d) 0.10 mm polyethylene. (2) Joints in sheet-type ground cover required in Sentence (1) shall be lapped not less than 100….

Insulated roof spaces are vented at 1/300 of the insulated ceiling area. Use 1/150 where the slope is under 1 in 6 or the roof uses roof joists OBC Div. B 9.19.1.2.OBC Div. B 9.19.1.2. Vent Requirements(1) Except as provided in Sentence (2), the unobstructed vent area shall be not less than 1/300 of the insulated ceiling area. (2) Where the roof slope is less than 1 in 6 or in roofs that are constructed with roof joists, the unobstructed vent area shall be not less than 1/150 of the insulated ceiling area. (3)…. Leave 63 mm between insulation and sheathing in vented joist spaces OBC Div. B 9.19.1.3.OBC Div. B 9.19.1.3. Clearances(1) Except as provided in Sentence (2), where venting is provided to a roof joist space, not less than 63 mm of space shall be provided between the top of the insulation and the underside of the roof sheathing. (2) Where venting is provided at the junction of sloped roofs and exterior walls and where preformed baffles…. An attic hatch of 550 mm by 900 mm is needed where the space is at least 10 m2, 1,000 mm long or wide and 600 mm high, or holds a fuel-fired appliance. One dwelling unit may use 0.32 m2 with no side under 500 mm OBC Div. B 9.19.2.1.OBC Div. B 9.19.2.1. Access(1) Every attic or roof space shall be provided with an access hatch where the attic or roof space (a) measures not less than (i) 10 m² in area, (ii) 1,000 mm in length or width, and (iii) 600 mm in height over at least the area described in Subclauses (i) and (ii), or (b) contains a fuel-fired appliance. (See Note….

Practice this topic

Masonry, chimneys and fireplaces

Masonry veneer is at least 70 mm thick, with a 25 mm air space over wood frame OBC Div. B 9.20.6.4.OBC Div. B 9.20.6.4. Masonry Veneer(1) Except for masonry veneer where each masonry unit is supported individually by the structural backing, masonry veneer shall consist of solid masonry units not less than 70 mm thick. (2) Veneer described in Sentence (1) over wood-frame walls shall have not less than a 25 mm air space behind the veneer. (3) Masonry…. Ties must meet the strap rules and the spacing table OBC Div. B 9.20.9.5.OBC Div. B 9.20.9.5. Ties for Masonry Veneer(1) Masonry veneer 70 mm or more in thickness and resting on a bearing support shall be tied to masonry backing or to wood framing members with straps that are (a) corrosion-resistant, (b) not less than 0.76 mm thick, (c) not less than 22 mm wide, (d) shaped to provide a key with the mortar, (e) pre-bent during…. Weep holes go at the bottom of cavities at no more than 800 mm apart OBC Div. B 9.20.13.8.OBC Div. B 9.20.13.8. Required Weep Holes(1) Weep holes spaced not more than 800 mm apart shall be provided at the bottom of (a) cavities in cavity walls, and (b) cavities or air spaces in masonry veneer walls. (2) The cavities or air spaces described in Sentence (1) shall include those above lintels over window and door openings required to be flashed in….

Section 9.21 covers site-built masonry or concrete chimneys up to 12 m high OBC Div. B 9.21.1.1.OBC Div. B 9.21.1.1. Application(1) This Section applies to, (a) rectangular masonry or concrete chimneys not more than 12 m in height serving fireplaces or serving appliances having a combined total rated heat output of 120 kW or less, and (b) flue pipes serving solid fuel-burning appliances. (2) Reserved. (3) Except as provided in Sentence…. The flue must extend at least 900 mm above the highest point of roof contact and 600 mm above any roof or structure within 3 m. Both tests apply, and the higher one governs OBC Div. B 9.21.4.4.OBC Div. B 9.21.4.4. Height of Chimney Flues(1) A chimney flue shall extend not less than (a) 900 mm above the highest point at which the chimney comes in contact with the roof, and (b) 600 mm above the highest roof surface or structure within 3 m of the chimney. (See Note A-9.21.4.4.(1)). Clearance to combustible framing is 50 mm inside and 12 mm for exterior chimneys OBC Div. B 9.21.5.1.OBC Div. B 9.21.5.1. Clearance from CombustibleMaterials(1) The clearance between masonry or concrete chimneys and combustible framing material shall be not less than, (a) 50 mm for interior chimneys, and (b) 12 mm for exterior chimneys. (See Note A-9.21.5.1.(1)) (2) A clearance of not less than 150 mm shall be provided between a cleanout opening and combustible material….

For fireplaces, the fire chamber is at least 300 mm deep OBC Div. B 9.22.4.1.OBC Div. B 9.22.4.1. Fire Chamber Dimensions(1) The distance from the back of the fire chamber to the plane of the fireplace opening shall be not less than 300 mm.. The hearth extends 400 mm in front and 200 mm to each side. It grows when the chamber floor is raised more than 150 mm above the hearth OBC Div. B 9.22.5.1.OBC Div. B 9.22.5.1. Hearth Extension(1) Except as required in Sentence (2), fireplaces shall have a noncombustible hearth extending not less than 400 mm in front of the fireplace opening measured from the facing, and not less than 200 mm beyond each side of the fireplace opening. (2) Where the fire chamber floor is elevated more than 150 mm above the….

Practice this topic

Wood-frame construction and span tables

Section 9.23 applies only within limits: members at no more than 600 mm o.c., live load not over 2.4 kPa and spans not over 12.20 m OBC Div. B 9.23.1.1.OBC Div. B 9.23.1.1. Limitations(1) This Section applies to constructions where wall, floor and roof planes are generally comprised of lumber frames of small repetitive structural members, or engineered components, and where (a) roof and wall planes are clad, sheathed or braced on at least one side, (b) the small repetitive structural members are…. Joist and rafter spans come from Span Tables 9.23.4.2.-A to -G. Built-up and glued-laminated floor beams use -H to -K, and roof ridge beams use -L OBC Div. B 9.23.4.2.OBC Div. B 9.23.4.2. Spans for Joists, Rafters and Beams(1) Except as required in Sentence (2) and Article 9.23.14.10., spans for wood joists and rafters shall conform to the spans shown in Span Tables 9.23.4.2.-A to 9.23.4.2-G for the uniform live loads shown in the Tables. (See Article 9.4.2.2.) (2) Spans for floor joists that are not selected from Span Tables…. Pick the table by member and load, then the row by species and grade, then the column by size and spacing.

Framing rule Limit Article
Holes in joists max 1/4 depth, 50 mm from edges 9.23.5.1
Notches in joists top only, within 1/2 depth of bearing, max 1/3 depth 9.23.5.2
Loadbearing stud after cutting keep 2/3 of depth 9.23.5.3
Joist end bearing 38 mm 9.23.9.1
Beam end bearing 89 mm 9.23.8.1

OBC Div. B 9.23.5.2.OBC Div. B 9.23.5.2. Notching of Framing Members(1) Floor, roof and ceiling framing members are permitted to be notched provided the notch is located on the top of the member within half the joist depth from the edge of bearing and is not deeper than one-third the joist depth, unless the depth of the member is increased by the size of the notch. and OBC Div. B 9.23.5.3.OBC Div. B 9.23.5.3. Wall Studs(1) Wall studs shall not be notched, drilled or otherwise damaged so that the undamaged portion of the stud is less than two-thirds the depth of the stud if the stud is loadbearing or 40 mm if the stud is non-loadbearing, unless the weakened studs are suitably reinforced. are favourite traps because holes and notches use different fractions. Stud size and spacing come from Table 9.23.10.1 OBC Div. B 9.23.10.1.OBC Div. B 9.23.10.1. Stud Size and Spacing(1) Except as provided in Sentence (2), the size and spacing of studs shall conform to Table 9.23.10.1. (2) Studs for walls not listed in Table 9.23.10.1. and supporting roof loads shall conform to Span Tables 9.23.10.1.-A to 9.23.10.1.-D, provided (a) the studs are clad with not less than 9.5 mm thick plywood, OSB or…. Floor joists carrying roof loads may cantilever 400 mm (38 x 184) or 600 mm (38 x 235 or larger) OBC Div. B 9.23.9.9.OBC Div. B 9.23.9.9. Cantilevered Floor Joists(1) Floor joists supporting roof loads shall not be cantilevered more than 400 mm beyond their supports where 38 mm by 184 mm joists are used and not more than 600 mm beyond their supports where 38 mm by 235 mm or larger joists are used. (2) The cantilevered portions referred to in Sentence (1) shall not support floor….

Practice this topic

Sheet steel stud framing

Section 9.24 covers only non-loadbearing steel studs. Loadbearing steel studs are designed to Part 4 OBC Div. B 9.24.1.1.OBC Div. B 9.24.1.1. Application(1) This Section applies to sheet steel study for use in non-loadbearing exterior and interior walls. (2) Where loadbearing steel studs are used, they shall be designed in conformance with Part 4.. Interior studs have a metal thickness of at least 0.46 mm OBC Div. B 9.24.2.2.OBC Div. B 9.24.2.2. Thickness of Studs(1) Except as required in Article 9.24.2.4., steel studs in non-loadbearing interior walls shall have a metal thickness of not less than 0.46 mm.. Runners have 30 mm flanges OBC Div. B 9.24.2.3.OBC Div. B 9.24.2.3. Runners(1) Runners for interior and exterior non-loadbearing walls shall have a thickness not less than the thickness of the corresponding studs and shall have not less than 30 mm flanges.. In fire-rated walls, leave 12 mm between stud top and runner top so the stud can expand OBC Div. B 9.24.3.2.OBC Div. B 9.24.3.2. Fire-Rated Walls(1) Steel studs used in walls required to have a fire-resistance rating shall be installed so that there is not less than a 12 mm clearance between the top of the stud and the top of the runner to allow for expansion in the event of fire. (2) Except as provided in Article 9.24.3.6., studs in walls referred to in….

Practice this topic

Common traps

  • Footing tables count floors supported, then add for veneer or masonry storeys. Do not forget the adjustment, and do not use 130 mm for veneer.
  • The 1/150 roof vent ratio applies to low slopes and roof joists only.
  • The 500 by 700 mm crawl space access is for one dwelling unit only.
  • The radon rough-in applies to every building containing a residential occupancy.

Chapter review

Chapter at a glance

One line per section: the idea to carry into the exam. Then the answers that most often catch candidates out.

Usual exam traps

  • Footing tables count floors supported, then add for veneer or masonry storeys. Do not forget the adjustment, and do not use 130 mm for veneer.
  • The 1/150 roof vent ratio applies to low slopes and roof joists only.
  • The 500 by 700 mm crawl space access is for one dwelling unit only.
  • The radon rough-in applies to every building containing a residential occupancy.

Practice this chapter

Questions on Foundations, framing and structure (Part 9), in the exam format, every answer explained and cited to its article. Sign in to start; a free account gets the free questions.

Code cited in this chapter

Based on the official 2024 Building Code Compendium on ontario.ca.

© King's Printer for Ontario, 2024. Reproduced with permission.

  • OBC Div. B 9.12.2.1. Excavation to Undisturbed Soil

    (1)Excavations for foundations shall extend to undisturbed soil.

    Open OBC Div. B 9.12.2.1. in the code viewer
  • OBC Div. B 9.12.2.2. Minimum Depth of Foundations

    (1)Except as provided in Sentences (4) to (7), the minimum depth of foundations below finished ground level shall conform to Table 9.12.2.2.

    (2)Where a foundation is insulated in a manner that will reduce the heat flow to the soil beneath the footings, the foundation depth shall conform to that required for foundations containing no heated space. (See Note A-9.12.2.2.(2))

    (3)The minimum depth of foundations for exterior concrete steps with more than 2 risers shall conform to Sentences (1), (2) and (5).

    (4)Concrete steps with 1 and 2 risers are permitted to be laid on ground level.

    (5)The foundation depths required in Sentence (1) are permitted to be decreased where experience with local soil conditions shows that lesser depths are satisfactory, or where the foundation is designed for lesser depths.

    (6)The foundation depths required in Sentence (1) do not apply to foundations for

    (a)buildings

    (i)that are not of masonry or masonry veneer construction, and

    (ii)whose superstructure conforms with the requirements of the deformation resistance test in CSA Z240.2.1, "Structural requirements for manufactured homes," or

    (b)accessory buildings

    (i)that are not of masonry or masonry veneer construction,

    (ii)not more than 1 storey in building height,

    (iii)not more than 55 m² in building area, and

    (iv)where the distance from finished ground to the underside of the floor joists is not more than 600 mm.

    (7)The foundation depths required by Sentence (1) do not apply to foundations for decks and other accessible exterior platforms

    (a)of not more than 1 storey,

    (b)not more than 55 m² in area,

    (c)where the distance from finished ground to the underside of the floor joists is not more than 600 mm,

    (d)not supporting a roof, and

    (e)not attached to another structure, unless it can be demonstrated that differential movement will not adversely affect the performance of that structure.

    Open OBC Div. B 9.12.2.2. in the code viewer
  • OBC Div. B 9.12.3.3. Deleterious Debris and Boulders

    (1)Backfill that is within 600 mm of the foundation shall be free of deleterious debris and boulders larger than 250 mm diam. (See Note A-9.12.3.3.(1))

    (2)Except as permitted in Sentence (3), backfill shall not contain pyritic material or material that is susceptible to ice lensing in concentrations that will damage the building to a degree that would adversely affect its stability or the performance of assemblies separating dissimilar environments. (See Note A-9.4.4.4.(1))

    (3)Backfill with material of any concentration that is susceptible to ice lensing is permitted where foundation walls are

    (a)cast-in-place concrete,

    (b)concrete block insulated on the exterior, or

    (c)concrete block protected from the backfill by a material that serves as a slip plane.

    (See Note A-9.4.4.4.(1))

    Open OBC Div. B 9.12.3.3. in the code viewer
  • OBC Div. B 9.12.3.2. Grading of Backfill

    (1)Backfill shall be graded to prevent drainage towards the foundation after settling.

    Open OBC Div. B 9.12.3.2. in the code viewer
  • OBC Div. B 9.13.2.1. Required Dampproofing

    (1)Except as provided in Sentence (4) and Article 9.13.3.1., where the exterior finished ground level is at a higher elevation than the ground level inside the foundation walls, exterior surfaces of foundation walls below ground level shall be dampproofed.

    (2)Except as provided in Sentence (3) and Article 9.13.3.1., floors-on-ground shall be dampproofed.

    (3)Floors in garages, floors in unenclosed portions of buildings and floors installed over granular fill in conformance with Article 9.16.2.1. need not be dampproofed.

    (4)Dampproofing in Sentence (1) is not required where the exterior surfaces of foundation walls below ground level are waterproofed.

    Open OBC Div. B 9.13.2.1. in the code viewer
  • OBC Div. B 9.13.3.1. Required Waterproofing

    (1)Where hydrostatic pressure occurs, waterproofing is required for assemblies separating interior space from the ground to prevent the ingress of water into building assemblies and interior spaces.

    (2)Waterproofing is required for roofs of underground structures to prevent the ingress of water into building assemblies and interior spaces.

    Open OBC Div. B 9.13.3.1. in the code viewer
  • OBC Div. B 9.13.4.2. Protection from Soil Gas Ingress

    (1)Except as provided in Sentence (1.1), all wall, roof and floor assemblies in contact with the ground shall be constructed to resist the leakage of soil gas from the ground into the building in accordance with Subsection 9.25.3. or MMAH Supplementary Standard SB-9, "Requirements for Soil Gas Control."

    (1.1)Construction to resist leakage of soil gas into the building is not required for garages and unenclosed portions of buildings.

    (1.2)Where polyethylene is used to provide a barrier to soil gas ingress through floors-on-ground, it shall conform to CAN/CGSB-51.34-M, "Vapour Barrier, Polyethylene Sheet, for Use in Building Construction."

    (2)Unless the space between the air barrier system and the ground is designed to be accessible for the future installation of a subfloor depressurization system, dwelling units and buildings containing residential occupancies shall be provided with the rough-in for a radon extraction system conforming to Article 9.13.4.3.

    (3)Where buildings are used for occupancies other than those described in Sentence (2), protection from radon ingress and the means to address high radon concentrations in the future shall conform to

    (a)Article 9.13.4.3., or

    (b)Parts 5 and 6. (See Article 5.4.1.1. and 6.2.1.1.) (See Note A-9.13.4.2.(3))

    Open OBC Div. B 9.13.4.2. in the code viewer
  • OBC Div. B 9.13.4.3. Providing for the Rough-in for a Subfloor Depressurization System

    (1)Floors-on-ground shall be provided with a rough-in for subfloor depressurization consisting of

    (a)a gas-permeable layer, an inlet and an outlet as described in Sentence (2), or

    (b)clean granular material and a pipe as described in Sentence (3).

    (2)The rough-in referred to in Clause (1)(a) shall include

    (a)a gas-permeable layer installed in the space between the air barrier and the ground to allow the depressurization of that space,

    (b)an inlet that allows for the effective depressurization of the gas-permeable layer, and (See Note A-9.13.4.3.(2) (b) and (3)(b)(i))

    (c)an outlet in the conditioned space that

    (i)permits connection to depressurization equipment,

    (ii)is sealed to maintain the integrity of the air barrier system, and

    (iii)is clearly labeled to indicate that it is intended only for the removal of radon from below the floor-on-ground.

    (3)The rough-in referred to in Clause (1)(b) shall include

    (a)clean granular material installed below the floor-on-ground in accordance with Sentence 9.16.2.1.(1), and

    (b)pipe not less than 100 mm in diameter installed through the floor, such that

    (i)its bottom end opens into the granular layer required in Clause (a) at or near the centre of the floor and not less than 100 mm of granular material projects beyond the terminus of the pipe measured along its axis, (See Note A-9.13.4.3.(2) (b) and (3)(b)(i))

    (ii)its top end permits connection to depressurization equipment and is provided with an airtight cap, and

    (iii)the pipe is clearly labeled near the cap and, if applicable, every 1.8 m and at every change in direction to indicate that it is intended only for the removal of radon from below the floor-on-ground.

    Open OBC Div. B 9.13.4.3. in the code viewer
Show all 48 articles
  • OBC Div. B 9.14.5.1. Drainage Disposal

    (1)Foundation drains shall drain to a sewer, drainage ditch or dry well.

    Open OBC Div. B 9.14.5.1. in the code viewer
  • OBC Div. B 9.15.1.1. General

    (1)Except as provided in Articles 9.15.1.2. and 9.15.1.3., this Section applies to

    (a)concrete or unit masonry foundation walls and concrete footings not subject to surcharge

    (i)on stable soils with an allowable bearing pressure of 75 kPa or greater, and

    (ii)for buildings of wood-frame or masonry construction,

    (b)wood-frame foundation walls and wood or concrete footings not subject to surcharge

    (i)on stable soils with an allowable bearing pressure of 75 kPa or greater, and

    (ii)for buildings of wood-frame construction, and

    (c)flat insulating concrete form foundation walls and concrete footings not subject to surcharge (See Note A-9.15.1.1.(1) (c) and 9.20.1.1.(1)(b))

    (i)on stable soils with an allowable bearing pressure of 75 kPa or greater, and

    (ii)for buildings of light-frame or flat insulating concrete form construction that are not more than 2 storeys in building height, with a maximum floor-to-floor height of 3 m.

    (2)Foundations for applications other than as described in Sentence (1) shall be designed in accordance with Section 9.4.

    (3)Where a foundation is erected on filled ground, peat or sensitive clay, the footing sizes shall be designed in conformance with Section 4.2.

    (4)For the purpose of Sentence (3), sensitive clay means the grain size of the majority of the particles is smaller than 0.002 mm, including leda clay.

    Open OBC Div. B 9.15.1.1. in the code viewer
  • OBC Div. B 9.15.3.3. Application of Footing Width and Area Requirements

    (1)Except as provided in Sentence 9.15.3.4.(2), the minimum footing width or area requirements provided in Articles 9.15.3.4. to 9.15.3.7. shall apply to footings, where

    (a)the footings support

    (i)foundation walls of masonry, concrete, or flat insulating concrete form walls,

    (ii)above ground walls of masonry, flat insulating concrete form walls or light wood-frame construction, and

    (iii)floors and roofs of light wood-frame construction,

    (b)the span of supported joists does not exceed 4.9 m, and

    (c)the specified live load on any floor supported by the footing does not exceed 2.4 kPa. (See Table 4.1.5.3.)

    (2)Except as provided in Sentence 9.15.3.4.(2), where the span of the supported joists exceeds 4.9 m, footings shall be designed in accordance with Section 4.2.

    (3)Where the specified live load exceeds 2.4 kPa footings shall be designed in accordance with Section 4.2.

    Open OBC Div. B 9.15.3.3. in the code viewer
  • OBC Div. B 9.15.3.4. Basic Footing Widths and Areas

    (1)Except as provided in Sentences (2) and (3) and in Articles 9.15.3.5. to 9.15.3.7., the minimum footing width or area shall comply with Table 9.15.3.4.

    (2)Where the supported joist span exceeds 4.9 m in buildings with light wood-frame walls, floors and roofs, strip footing widths shall be determined according to

    (a)Section 4.2., or

    (b)the following formula:

    W = w × [∑sjs/(storeys × 4.9)]

    where

    W = minimum footing width,

    w = minimum width of footings supporting joists not exceeding 4.9 m, as defined by Table 9.15.3.4.,

    ∑ sjs = sum of the supported joist spans on each storey bearing on an exterior wall whose load is transferred to the footing, or sum of half of the supported joist spans on each storey bearing on both sides of an interior wall whose load is transferred to the footing, and

    storeys = number of storeys supported by the footing. (See Note A-9.15.3.4.(2))

    (3)Where a foundation rests on gravel, sand or silt in which the water table level is less than the width of the footings below the bearing surface,

    (a)the footing width for walls shall be not less than twice the width required by Sentences (1) and (2), and Articles 9.15.3.5. and 9.15.3.6., and

    (b)the footing area for columns shall be not less than twice the area required by Sentences (1) and (2) and Article 9.15.3.7.

    Open OBC Div. B 9.15.3.4. in the code viewer
  • OBC Div. B 9.15.3.5. Adjustments to Footing Widths for Exterior Walls

    (1)The strip footing widths for exterior walls shown in Table 9.15.3.4. shall be increased by

    (a)65 mm for each storey of masonry veneer over wood-frame construction supported by the foundation wall,

    (b)130 mm for each storey of masonry construction supported by the foundation wall, and

    (c)150 mm for each storey of flat insulating concrete form wall construction supported by the foundation wall.

    Open OBC Div. B 9.15.3.5. in the code viewer
  • OBC Div. B 9.15.3.8. Footing Thickness

    (1)Footing thickness shall be not less than the greater of

    (a)100 mm, or

    (b)the width of the projection of the footing beyond the supported element.

    Open OBC Div. B 9.15.3.8. in the code viewer
  • OBC Div. B 9.15.3.9. Step Footings

    (1)Where step footings are used,

    (a)the vertical rise between horizontal portions shall not exceed 600 mm, and

    (b)the horizontal distance between risers shall be not less than 600 mm.

    Open OBC Div. B 9.15.3.9. in the code viewer
  • OBC Div. B 9.15.4.6. Extension Above Ground Level

    (1)Exterior foundation walls shall extend not less than 150 mm above finished ground level.

    Open OBC Div. B 9.15.4.6. in the code viewer
  • OBC Div. B 9.15.4.2. Foundation Wall Thickness and Required Lateral Support

    (1)Except as required in Sentence (2), the thickness of foundation walls made of unreinforced concrete block, concrete core in flat wall insulating concrete forms or solid concrete and subject to lateral earth pressure shall conform to Table 9.15.4.2.-A for walls not exceeding 3.0 m in unsupported height.

    (2)The concrete core in flat insulating concrete form foundation walls shall be not less than the greater of

    (a)150 mm, or

    (b)the thickness of the concrete in the wall above.

    (2.1)Foundation walls made of flat insulating concrete form units shall be laterally supported at the top and at the bottom.

    (3)The thickness and reinforcing of foundation walls made of reinforced concrete block and subject to lateral earth pressure shall conform to Table 9.15.4.2.-B and Sentences (4) to (7), where

    (a)the walls are laterally supported at the top,

    (b)average stable soils are encountered, and

    (c)wind loads on the exposed portion of the foundation are no greater than 0.70 kPa.

    (4)For concrete block walls required to be reinforced, continuous vertical reinforcement shall

    (a)be provided at wall corners, wall ends, wall intersections, at changes in wall height, at the jambs of all openings and at movement joints.

    (b)extend from the top of the footing to the top of the foundation wall, and

    (c)where foundation walls are laterally supported at the top, have not less than 50 mm embedment into the footing, if the floor slab does not provide lateral support at the wall base.

    (5)For concrete block walls required to be reinforced, a continuous horizontal bond beam containing not less than one 15 M bar shall be installed

    (a)along the top of the wall,

    (b)at the sill and head of all openings greater than 1.20 m in width, and

    (c)at structurally connected floors.

    (6)In concrete block walls required to be reinforced, all vertical bar reinforcement shall be installed along the centre line of the wall.

    (7)In concrete block walls required to be reinforced, ladder- or truss-type lateral reinforcement not less than 3.8 mm in diameter (No. 9 ASWG) shall be installed in the bed joint of every second masonry course.

    Open OBC Div. B 9.15.4.2. in the code viewer
  • OBC Div. B 9.15.4.3. Foundation Walls Considered to be Laterally Supported at the Top

    (1)Sentences (2) to (4) pertain to lateral support for walls described in Sentence 9.15.4.2.(1).

    (2)Foundation walls shall be considered to be laterally supported at the top if

    (a)such walls support a solid masonry superstructure or flat insulating concrete form wall,

    (b)the floor joists are embedded in the top of the foundation walls,

    (c)the floor system is anchored to the top of the foundation walls with anchor bolts, in which case the joists may run either parallel or perpendicular to the foundation walls, or

    (d)they extend from the footing to no more than 300 mm above the finished ground level and are backfilled on both sides such that the difference in elevation between the finished ground levels on either side of the wall is no more than 150 mm.

    (3)Unless the wall around an opening is reinforced to withstand earth pressure, the portion of the foundation wall beneath an opening shall be considered laterally unsupported if

    (a)the opening is more than 1.2 m wide, or

    (b)the total width of the openings in the foundation wall constitutes more than 25% of the length of the wall.

    (4)For the purposes of Sentence (3), the combined width of the openings shall be considered as a single opening if the average width is greater than the width of solid wall between them.

    (5)Flat insulating concrete form foundation walls shall be considered to be laterally supported at the top if the floor joists are installed according to Article 9.20.17.5.

    Open OBC Div. B 9.15.4.3. in the code viewer
  • OBC Div. B 9.16.2.1. Required Installation of Granular Fill

    (1)Except as provided in Sentence (2), not less than 100 mm of coarse clean granular material containing not more than 10% of material that will pass a 4 mm sieve shall be placed beneath floors-on-ground. (See also Subsection 9.13.4. and Note A-9.13.4.)

    (2)Granular material need not be installed under

    (a)slabs in garages, carports or accessory buildings, or

    (b)buildings of industrial occupancy where the nature of the process contained therein permits or requires the use of large openings in the building envelope even during the winter.

    Open OBC Div. B 9.16.2.1. in the code viewer
  • OBC Div. B 9.16.4.3. Thickness

    (1)Concrete slabs shall be not less than 75 mm thick exclusive of concrete topping. (See Note A-9.16.4.3.(1))

    Open OBC Div. B 9.16.4.3. in the code viewer
  • OBC Div. B 9.17.2.1. Location

    (1)Columns shall be centrally located on a footing conforming to Section 9.15.

    Open OBC Div. B 9.17.2.1. in the code viewer
  • OBC Div. B 9.17.3.1. Size and Thickness

    (1)Except as permitted in Sentence (2), steel pipe columns shall have an outside diameter of not less than 73 mm and a wall thickness of not less than 4.76 mm.

    (2)Columns of sizes other than as specified in Sentence (1) are permitted to be used where the loadbearing capacities are shown to be adequate.

    Open OBC Div. B 9.17.3.1. in the code viewer
  • OBC Div. B 9.17.4.1. Column Sizes

    (1)The width or diameter of a wood column shall be not less than the width of the supported member.

    (2)Except as provided in Article 9.35.4.2., columns shall be not less than 184 mm for round columns and 140 mm by 140 mm for rectangular columns, unless calculations are provided to show that lesser sizes are adequate.

    Open OBC Div. B 9.17.4.1. in the code viewer
  • OBC Div. B 9.18.1.3. Heated and Unheated Crawl Spaces

    (1)Crawl spaces shall be considered to be heated where the space

    (a)is used as a warm air plenum,

    (b)contains heating ducts or heating pipes that are not sealed and insulated to minimize heat loss to the space, or

    (c)is not separated from heated space in accordance with Section 9.25.

    (2)Heating of heated crawl spaces shall conform to Section 9.33.

    (3)Insulation, an air barrier system and a vapour barrier shall be installed in the walls of heated crawl spaces in accordance with Section 9.25.

    Open OBC Div. B 9.18.1.3. in the code viewer
  • OBC Div. B 9.18.2.1. Access Openings

    (1)An access opening of not less than 500 mm by 700 mm shall be provided to each crawl space where the crawl space serves a single dwelling unit, and not less than 550 mm by 900 mm for other crawl spaces.

    (2)Access openings shall be fitted with a door or hatch, except when the crawl space is heated and the access opening into the crawl space is from an adjacent heated space.

    Open OBC Div. B 9.18.2.1. in the code viewer
  • OBC Div. B 9.18.3.1. Ventilation of Unheated Crawl Spaces

    (1)Unheated crawl spaces shall be ventilated by natural or mechanical means.

    (2)Where an unheated crawl space is ventilated by natural means, ventilation shall be provided to the outside air by not less than 0.1 m² of unobstructed vent area for every 50 m² of floor area.

    (3)Vents shall be

    (a)uniformly distributed on opposite sides of the building, and

    (b)designed to prevent the entry of snow, rain and insects.

    Open OBC Div. B 9.18.3.1. in the code viewer
  • OBC Div. B 9.18.6.1. Ground Cover in Unheated Crawl Spaces

    (1)Where a crawl space is unheated, a ground cover shall be provided consisting of not less than

    (a)50 mm of asphalt,

    (b)100 mm of 15 MPa Portland cement concrete,

    (c)Type S roll roofing, or

    (d)0.10 mm polyethylene.

    (2)Joints in sheet-type ground cover required in Sentence (1) shall be lapped not less than 100 mm and weighted down.

    Open OBC Div. B 9.18.6.1. in the code viewer
  • OBC Div. B 9.19.1.2. Vent Requirements

    (1)Except as provided in Sentence (2), the unobstructed vent area shall be not less than 1/300 of the insulated ceiling area.

    (2)Where the roof slope is less than 1 in 6 or in roofs that are constructed with roof joists, the unobstructed vent area shall be not less than 1/150 of the insulated ceiling area.

    (3)Required vents may be roof type, eave type, gable-end type or any combination thereof, and shall be distributed

    (a)uniformly on opposite sides of the building,

    (b)with not less than 25% of the required openings located at the top of the space, and

    (c)with not less than 25% of the required openings located at the bottom of the space.

    (4)Except where each roof joist space referred to in Sentence (2) is separately vented, roof joist spaces shall be interconnected by installing purlins not less than 38 mm by 38 mm on the top of the roof joists.

    (5)Vents shall comply with CAN3-A93-M, "Natural Airflow Ventilators for Buildings."

    Open OBC Div. B 9.19.1.2. in the code viewer
  • OBC Div. B 9.19.1.3. Clearances

    (1)Except as provided in Sentence (2), where venting is provided to a roof joist space, not less than 63 mm of space shall be provided between the top of the insulation and the underside of the roof sheathing.

    (2)Where venting is provided at the junction of sloped roofs and exterior walls and where preformed baffles are used to contain the insulation, the baffles shall

    (a)provide an unobstructed air space, between the insulation and the underside of the roof sheathing, that is

    (i)not less than 25 mm in dimension, and

    (ii)of sufficient cross area to meet the attic or roof space venting requirements of Article 9.19.1.2., and

    (b)extend vertically not less than 50 mm above the top of the insulation.

    (3)Ceiling insulation shall be installed in a manner that will not restrict the free flow of air through roof vents or through any portion of the attic or roof space.

    Open OBC Div. B 9.19.1.3. in the code viewer
  • OBC Div. B 9.19.2.1. Access

    (1)Every attic or roof space shall be provided with an access hatch where the attic or roof space

    (a)measures not less than

    (i)10 m² in area,

    (ii)1,000 mm in length or width, and

    (iii)600 mm in height over at least the area described in Subclauses (i) and (ii), or

    (b)contains a fuel-fired appliance. (See Note A-9.19.2.1.(1))

    (2)The hatch required in Sentence (1) shall be not less than 550 mm by 900 mm except that, where the hatch serves not more than one dwelling unit, the hatch may be reduced to 0.32 m² in area with no dimension less than 500 mm. (See Note A-9.19.2.1.(2))

    (3)Hatchways to attic or roof spaces shall be fitted with doors or covers.

    Open OBC Div. B 9.19.2.1. in the code viewer
  • OBC Div. B 9.20.6.4. Masonry Veneer

    (1)Except for masonry veneer where each masonry unit is supported individually by the structural backing, masonry veneer shall consist of solid masonry units not less than 70 mm thick.

    (2)Veneer described in Sentence (1) over wood-frame walls shall have not less than a 25 mm air space behind the veneer.

    (3)Masonry veneer less than 90 mm thick shall have unraked joints.

    (4)Masonry veneer shall conform to Subsection 4.3.2. where the masonry units are required to be individually supported by the structural backing.

    Open OBC Div. B 9.20.6.4. in the code viewer
  • OBC Div. B 9.20.9.5. Ties for Masonry Veneer

    (1)Masonry veneer 70 mm or more in thickness and resting on a bearing support shall be tied to masonry backing or to wood framing members with straps that are

    (a)corrosion-resistant,

    (b)not less than 0.76 mm thick,

    (c)not less than 22 mm wide,

    (d)shaped to provide a key with the mortar,

    (e)pre-bent during manufacture to a right angle within 6 mm of the fastener hole,

    (f)fastened with

    (i)corrosion-resistant wood screws conforming to Sentence 9.23.3.1.(3) that have a minimum diameter of 4.16 mm (No. 8) and a wood penetration of not less than 38 mm, or

    (ii)corrosion-resistant common spiral nails conforming to Sentence 9.23.3.1.(1) that are not less than 76 mm long and have a wood penetration of not less than 63 mm, and

    (g)spaced in accordance with Table 9.20.9.5.

    (2)Where hot-dipped, zinc-coated straps are used to meet the requirements of Sentence (1), they shall be pre-bent and pre-drilled or pre-punched prior to hot-dip, zinc-coated galvanizing.

    (3)Masonry veneer individually supported by masonry or wood-frame backing shall be secured to the backing in conformance with Subsection 4.3.2.

    (4)The straps described in Sentence (1) may be installed against one of the sheathings listed in Table 9.23.17.2.-A provided that

    (a)the tie is in contact with the exterior surface of the sheathing, and

    (b)the sheathing beneath the tie is not compressed.

    Open OBC Div. B 9.20.9.5. in the code viewer
  • OBC Div. B 9.20.13.8. Required Weep Holes

    (1)Weep holes spaced not more than 800 mm apart shall be provided at the bottom of

    (a)cavities in cavity walls, and

    (b)cavities or air spaces in masonry veneer walls.

    (2)The cavities or air spaces described in Sentence (1) shall include those above lintels over window and door openings required to be flashed in conformance with Article 9.20.13.3.

    (3)The weep holes required in Sentence (1) shall be in a location such that any water that collects in the cavity or space will be directed to the exterior of the building.

    Open OBC Div. B 9.20.13.8. in the code viewer
  • OBC Div. B 9.21.1.1. Application

    (1)This Section applies to,

    (a)rectangular masonry or concrete chimneys not more than 12 m in height serving fireplaces or serving appliances having a combined total rated heat output of 120 kW or less, and

    (b)flue pipes serving solid fuel-burning appliances.

    (2)Reserved.

    (3)Except as provided in Sentence 9.21.1.3.(1), chimneys (other than those described in Sentence (1) and Sentence 9.21.1.2.(1)), gas vents and flue pipes serving gas-, oil- or solid fuel-burning appliances and associated equipment shall conform to Section 6.3.

    Open OBC Div. B 9.21.1.1. in the code viewer
  • OBC Div. B 9.21.4.4. Height of Chimney Flues

    (1)A chimney flue shall extend not less than

    (a)900 mm above the highest point at which the chimney comes in contact with the roof, and

    (b)600 mm above the highest roof surface or structure within 3 m of the chimney. (See Note A-9.21.4.4.(1))

    Open OBC Div. B 9.21.4.4. in the code viewer
  • OBC Div. B 9.21.5.1. Clearance from CombustibleMaterials

    (1)The clearance between masonry or concrete chimneys and combustible framing material shall be not less than,

    (a)50 mm for interior chimneys, and

    (b)12 mm for exterior chimneys. (See Note A-9.21.5.1.(1))

    (2)A clearance of not less than 150 mm shall be provided between a cleanout opening and combustible material.

    (3)Combustible flooring, subflooring and ceiling finishes shall have not less than a 12 mm clearance from masonry or concrete chimneys.

    Open OBC Div. B 9.21.5.1. in the code viewer
  • OBC Div. B 9.22.4.1. Fire Chamber Dimensions

    (1)The distance from the back of the fire chamber to the plane of the fireplace opening shall be not less than 300 mm.

    Open OBC Div. B 9.22.4.1. in the code viewer
  • OBC Div. B 9.22.5.1. Hearth Extension

    (1)Except as required in Sentence (2), fireplaces shall have a noncombustible hearth extending not less than 400 mm in front of the fireplace opening measured from the facing, and not less than 200 mm beyond each side of the fireplace opening.

    (2)Where the fire chamber floor is elevated more than 150 mm above the hearth, the dimension of the hearth measured perpendicular to the plane of the fireplace opening shall be increased by not less than

    (a)50 mm for an elevation above 150 mm and not more than 300 mm, and

    (b)an additional 25 mm for every 50 mm in elevation above 300 mm.

    Open OBC Div. B 9.22.5.1. in the code viewer
  • OBC Div. B 9.23.1.1. Limitations

    (1)This Section applies to constructions where wall, floor and roof planes are generally comprised of lumber frames of small repetitive structural members, or engineered components, and where

    (a)roof and wall planes are clad, sheathed or braced on at least one side,

    (b)the small repetitive structural members are spaced not more than 600 mm o.c.,

    (c)the constructions do not serve as foundations,

    (d)the specified live load on supported subfloors and floor framing does not exceed 2.4 kPa, and

    (e)the span of any structural member does not exceed 12.20 m. (See Note A-9.23.1.1.(1))

    (2)Where the conditions in Sentence (1) are exceeded for wood construction, the design of the framing and fastening shall conform to Subsection 4.3.1.

    Open OBC Div. B 9.23.1.1. in the code viewer
  • OBC Div. B 9.23.4.2. Spans for Joists, Rafters and Beams

    (1)Except as required in Sentence (2) and Article 9.23.14.10., spans for wood joists and rafters shall conform to the spans shown in Span Tables 9.23.4.2.-A to 9.23.4.2-G for the uniform live loads shown in the Tables. (See Article 9.4.2.2.)

    (2)Spans for floor joists that are not selected from Span Tables 9.23.4.2.-A and 9.23.4.2-B and that are required to be designed for the same loading conditions, shall not exceed the design requirements for uniform loading and vibration criteria. (See Note A-9.23.4.2.(2))

    (3)Spans for built-up wood and glued-laminated timber floor beams shall conform to the spans in Span Tables 9.23.4.2.-H to 9.23.4.2-K. (See Article 9.4.2.2.)

    (4)Spans for roof ridge beams shall conform to the spans in Span Table 9.23.4.2.-L for the uniform snow load shown. (See Articles 9.4.2.2. and 9.23.14.8.)

    Open OBC Div. B 9.23.4.2. in the code viewer
  • OBC Div. B 9.23.5.2. Notching of Framing Members

    (1)Floor, roof and ceiling framing members are permitted to be notched provided the notch is located on the top of the member within half the joist depth from the edge of bearing and is not deeper than one-third the joist depth, unless the depth of the member is increased by the size of the notch.

    Open OBC Div. B 9.23.5.2. in the code viewer
  • OBC Div. B 9.23.5.3. Wall Studs

    (1)Wall studs shall not be notched, drilled or otherwise damaged so that the undamaged portion of the stud is less than two-thirds the depth of the stud if the stud is loadbearing or 40 mm if the stud is non-loadbearing, unless the weakened studs are suitably reinforced.

    Open OBC Div. B 9.23.5.3. in the code viewer
  • OBC Div. B 9.23.10.1. Stud Size and Spacing

    (1)Except as provided in Sentence (2), the size and spacing of studs shall conform to Table 9.23.10.1.

    (2)Studs for walls not listed in Table 9.23.10.1. and supporting roof loads shall conform to Span Tables 9.23.10.1.-A to 9.23.10.1.-D, provided

    (a)the studs are clad with not less than 9.5 mm thick plywood, OSB or waferboard sheathing on the exterior face, and not less than 12.5 mm gypsum board on the interior face,

    (b)solid bridging is provided at not more than 1.2 m o.c,

    (c)the studs are fastened to the top and bottom plates with no fewer than three 82 mm toe nails,

    (d)the double top plates are fastened together with not less than 76 mm nails spaced not more than 200 mm o.c,

    (e)roof framing members spaced not more than 600 mm are fastened to the top plates with no fewer than four 82 mm toe nails, and

    (f)the bottom plate is fastened to the floor joists, blocking or rim joist with not less than 82 mm nails spaced not more than 200 mm o.c.

    (See Note A-9.23.10.1.(2))

    Open OBC Div. B 9.23.10.1. in the code viewer
  • OBC Div. B 9.23.9.9. Cantilevered Floor Joists

    (1)Floor joists supporting roof loads shall not be cantilevered more than 400 mm beyond their supports where 38 mm by 184 mm joists are used and not more than 600 mm beyond their supports where 38 mm by 235 mm or larger joists are used.

    (2)The cantilevered portions referred to in Sentence (1) shall not support floor loads from other storeys unless calculations are provided to show that the design resistances of the cantilevered joists are not exceeded.

    (3)Where cantilevered floor joists described in Sentences (1) and (2) are at right angles to the main floor joists, the tail joists in the cantilevered portion shall extend inward away from the cantilever support a distance equal to not less than 6 times the length of the cantilever, and shall be end nailed to an interior doubled header joist in conformance with Table 9.23.3.4.

    Open OBC Div. B 9.23.9.9. in the code viewer
  • OBC Div. B 9.24.1.1. Application

    (1)This Section applies to sheet steel study for use in non-loadbearing exterior and interior walls.

    (2)Where loadbearing steel studs are used, they shall be designed in conformance with Part 4.

    Open OBC Div. B 9.24.1.1. in the code viewer
  • OBC Div. B 9.24.2.2. Thickness of Studs

    (1)Except as required in Article 9.24.2.4., steel studs in non-loadbearing interior walls shall have a metal thickness of not less than 0.46 mm.

    Open OBC Div. B 9.24.2.2. in the code viewer
  • OBC Div. B 9.24.2.3. Runners

    (1)Runners for interior and exterior non-loadbearing walls shall have a thickness not less than the thickness of the corresponding studs and shall have not less than 30 mm flanges.

    Open OBC Div. B 9.24.2.3. in the code viewer
  • OBC Div. B 9.24.3.2. Fire-Rated Walls

    (1)Steel studs used in walls required to have a fire-resistance rating shall be installed so that there is not less than a 12 mm clearance between the top of the stud and the top of the runner to allow for expansion in the event of fire.

    (2)Except as provided in Article 9.24.3.6., studs in walls referred to in Sentence (1) shall not be attached to the runners in a manner that will prevent such expansion.

    (3)Framing above doors with steel door frames in non-loadbearing fire separations required to have a fire-resistance rating shall consist of 2 runners on the flat fastened back to back. (See Note A-9.24.3.2.(3))

    (4)The lower runner required in Sentence (3) shall be cut through the flanges and be bent at each end to extend upwards at least 150 mm and fastened to the adjacent studs.

    Open OBC Div. B 9.24.3.2. in the code viewer