Values this chapter turns on

after issuance, work must be seriously commenced
6 months
after issuance, work must be seriously commenced
suspension of work longer than this allows revocation
1 year
suspension of work longer than this allows revocation
after notice of completion before occupancy, if not inspected
10 days
after notice of completion before occupancy, if not inspected
on which the CBO may revoke a permit
6 grounds
on which the CBO may revoke a permit

Sections 8 to 14 of the Act cover building and demolition permits, conditional permits, revocation, change of use permits, notices of readiness for inspection, occupancy after completion, inspections and orders, orders not to cover and stop work orders. Numbers matter here: six months, one year, ten days, and the grounds listed in each subsection.

Building permits, refusals and conditional permits

The basic rule: "No person shall construct or demolish a building or cause a building to be constructed or demolished unless a permit has been issued therefor by the chief building official" (BCA s. 8(1)BCA s. 8 Building permits(1) No person shall construct or demolish a building or cause a building to be constructed or demolished unless a permit has been issued therefor by the chief building official. (1.1) An application for a permit to construct or demolish a building may be made by a person specified by regulation and the prescribed form…). An application is made by a person specified by regulation, on the prescribed or Minister-approved form, with the specified documents (s. 8(1.1)).

The CBO "shall issue" the permit unless one of the grounds in s. 8(2) applies:

Clause Ground for refusal
(a) it would contravene the Act, the building code "or any other applicable law"
(b) the applicant is an unlicensed builder or vendor under the New Home Construction Licensing Act, 2017
(b.1) the Architects Act or Professional Engineers Act requires an architect or engineer and the design is not by one
(c) a designer lacks required qualifications or insurance
(d) a required plans review certificate lacks the prescribed information
(e) the application is not complete
(f) fees due have not been paid

If a valid plans review certificate accompanies the application, the CBO cannot refuse on the ground that the design does not comply with the code (s. 8(2.1)). A complete application must be decided within the prescribed period, and on refusal the CBO must give "all of the reasons" within the prescribed period (s. 8(2.2), (2.3)). The periods are set in Division C 1.3.1.3. (chapter 11).

Conditional permits. Even if not all requirements are met, the CBO may issue a conditional permit for any stage of construction if all three conditions in s. 8(3) are met:

  1. zoning (by-laws under sections 34 and 38 of the Planning Act) and other prescribed applicable law are complied with;
  2. the CBO believes "unreasonable delays in the construction would occur" without it; and
  3. the applicant (and others the CBO names) agree in writing to assume all risk, get approvals and file complete plans on time, remove the building and restore the site at their own expense if they fail, and meet other conditions, including security.

The CBO must consider how hard it would be to restore the site (s. 8(4)). The agreement can be registered on title (s. 8(5)). If the site is not restored, the CBO may do it and enter without a warrant (s. 8(6)); in a municipality the cost becomes a priority lien on the land (s. 8(7)). A refusal to issue a conditional permit cannot be appealed to court under section 25.

Revocation. Subject to section 25, the CBO may revoke a permit under BCA s. 8(10)BCA s. 8 Building permits(1) No person shall construct or demolish a building or cause a building to be constructed or demolished unless a permit has been issued therefor by the chief building official. (1.1) An application for a permit to construct or demolish a building may be made by a person specified by regulation and the prescribed form…:

Clause Ground
(a) issued on mistaken, false or incorrect information
(b) not "seriously commenced" six months after issuance
(c) "substantially suspended or discontinued for a period of more than one year"
(d) issued in error
(e) the holder asks in writing
(f) a term of a conditional permit agreement is broken

Changes after issue. No one may make a material change to the permit plans without notifying, filing details with and getting authorization from the CBO (s. 8(12)), and work must follow the permit documents (s. 8(13)). A change certificate with the prescribed information stops the CBO from refusing the change on code grounds (s. 8(14)).

Worked example: a stalled project

A permit was issued on March 1. Work started in April, then stopped completely in June and has not resumed by the following August, 14 months later. The CBO may revoke under s. 8(10)(c), because work has been substantially suspended for more than one year. Clause (b) does not apply, because work was seriously commenced within six months.

Practice this topic

Change of use permits and the sewage system prohibition

Even with no construction, no one may change the use of a building or part of it "if the change would result in an increase in hazard, as determined in accordance with the building code", without a permit (BCA s. 10(1)BCA s. 10 Change of use(1) Even though no construction is proposed, no person shall change the use of a building or part of a building or permit the use to be changed if the change would result in an increase in hazard, as determined in accordance with the building code, unless a permit has been issued by the chief building official. (2)…). The CBO must issue it unless the new use would contravene the Act, code or other applicable law, the application is incomplete, or fees are unpaid (s. 10(2)). Division C 1.3.1.4. defines which changes are an increase in hazard.

Section 10.1 is a one-line rule: no one may "operate or maintain a sewage system or permit a sewage system to be operated or maintained except in accordance with this Act and the building code" (BCA s. 10.1BCA s. 10.1 Prohibition re sewage systemsNo person shall operate or maintain a sewage system or permit a sewage system to be operated or maintained except in accordance with this Act and the building code.). This is what lets maintenance programs and unsafe sewage system orders work.

Practice this topic

Notice of readiness, inspections and occupancy

At each stage set in the code, the prescribed person must notify the CBO (or RCA) that construction is ready for inspection, and an inspector or RCA must inspect within the prescribed period (BCA s. 10.2BCA s. 10.2 Notice of readiness for inspection(1) At each stage of construction specified in the building code, the prescribed person shall notify the chief building official or the registered code agency, if any, that the construction is ready to be inspected. (2) After the notice is received, an inspector or the registered code agency, as the case may be, shall…). Division C sets the periods: two days for most notices, five days for sewage system notices (OBC Div. C 1.3.5.3.OBC Div. C 1.3.5.3. Prescribed Inspections(1) Except as provided in Sentence (2), an inspector or registered code agency, as the case may be, shall, not later than two days after receipt of a notice given under Sentence 1.3.5.1.(2), undertake a site inspection of the building to which the notice relates. (2) Where a notice given under Sentence 1.3.5.1.(2)…).

Occupancy after completion. A newly erected or installed building may not be occupied until the section 11 requirements are met, unless the code authorizes it (BCA s. 11BCA s. 11 Occupancy or use after completion(1) Except as authorized by the building code, a person shall not occupy or use a building or part of a building that is newly erected or installed or permit it to be occupied or used until the requirements set out in this section are met. (2) Notice of the date of completion of the building or part must be given to…):

  • notice of the date of completion goes to the CBO or RCA;
  • where an RCA was appointed for post-permit functions, a final certificate with the prescribed information must be issued;
  • otherwise, the building must be inspected "or 10 days must elapse after notice of the date of completion is served", and any section 12 order must be complied with.

Inspections and orders. An inspector may enter land and buildings "at any reasonable time without a warrant" to check compliance with the Act, the code or an order (BCA s. 12(1)BCA s. 12 Inspection of buildings and building sites(1) An inspector may enter upon land and into buildings at any reasonable time without a warrant for the purpose of inspecting the building or site to determine whether or not the following are being complied with: 1. This Act. 2. The building code. 3. An order made under this Act. (2) An inspector who finds a…). On finding a contravention, the inspector may order compliance, immediately or within a stated time, served on the person believed to be contravening (s. 12(2), (3)). The order must use the prescribed or approved form and describe the contravention, its location and the compliance needed (s. 12(4)). It may be posted on site, published, and registered on title; a later buyer is then deemed served (s. 12(5), (6)).

Practice this topic

Order not to cover and stop work orders

An inspector may order that part of a building not be covered or enclosed pending inspection (BCA s. 13(1)BCA s. 13 Order not to cover(1) An inspector may make an order prohibiting the covering or enclosing of any part of a building pending inspection. (1.1) The prescribed form or the form approved by the Minister must be used for an order made under this section. (2) The order shall be served on the person to whom the permit is issued, if any, and…). It is served on the permit holder and others the inspector chooses. The inspection must follow "within a reasonable time" after notice that the part is ready.

The CBO or RCA may order work uncovered at the builder's expense if they believe covered work does not comply and, for example, it was covered contrary to an order, a required notice was not given, the inspection period had not elapsed, or there was no permit (s. 13(6)).

Stop work order. If an order under section 12 or 13 is not complied with within the stated time, or a reasonable time if none, the CBO or RCA "may order that all or any part of the construction or demolition cease" (BCA s. 14(1)BCA s. 14 Stop work order(1) If an order made under section 12 or 13 is not complied with within the time specified in it, or where no time is specified, within a reasonable time, the chief building official or registered code agency, as the case may be, may order that all or any part of the construction or demolition cease. (1.1) The…). It must be on the prescribed or approved form, served on affected persons and posted on site, and "The order is effective from the time it is posted" (s. 14(3)). While it stands, only work needed to carry out the underlying section 12 or 13 order is allowed (s. 14(4)).

Order Who makes it Served on
Compliance order, s. 12 inspector the person believed to be contravening
Order not to cover, s. 13(1) inspector the permit holder, if any, and others affected
Order to uncover, s. 13(6) CBO or RCA directed to the persons responsible for the construction
Stop work order, s. 14 CBO or RCA affected persons, plus a copy posted on site (effective from posting)

Practice this topic

Common traps

  • Six months vs one year. Not seriously commenced: six months. Suspended: more than one year.
  • Conditional permits need all three s. 8(3) conditions, including zoning compliance.
  • Change of use needs a permit only if there is an increase in hazard as set by the code.
  • Stop work orders follow an unmet section 12 or 13 order; an inspector cannot issue one alone.
  • Occupancy without an RCA final certificate: inspection, or 10 days after notice of completion.

Chapter review

Chapter at a glance

One line per section: the idea to carry into the exam. Then the answers that most often catch candidates out.

Usual exam traps

  • Six months vs one year. Not seriously commenced: six months. Suspended: more than one year.
  • Conditional permits need all three s. 8(3) conditions, including zoning compliance.
  • Change of use needs a permit only if there is an increase in hazard as set by the code.
  • Stop work orders follow an unmet section 12 or 13 order; an inspector cannot issue one alone.
  • Occupancy without an RCA final certificate: inspection, or 10 days after notice of completion.

Practice this chapter

Questions on Permits, construction and demolition, in the exam format, every answer explained and cited to its article. Sign in to start; a free account gets the free questions.

Code cited in this chapter

Based on the official 2024 Building Code Compendium on ontario.ca.

© King's Printer for Ontario, 2024. Reproduced with permission.

  • BCA s. 8 Building permits

    (1)No person shall construct or demolish a building or cause a building to be constructed or demolished unless a permit has been issued therefor by the chief building official.

    (1.1)An application for a permit to construct or demolish a building may be made by a person specified by regulation and the prescribed form or the form approved by the Minister must be used and be accompanied by the documents and information specified by regulation.

    (2)The chief building official shall issue a permit referred to in subsection (1) unless,

    (a)the proposed building, construction or demolition will contravene this Act, the building code or any other applicable law;

    (b)the applicant is a builder or vendor as defined in subsection 1 (1) of the New Home Construction Licensing Act, 2017 and is not licensed under that Act;

    (b.1) the Architects Act or the Professional Engineers Act requires that the proposed construction of the building be designed by an architect or a professional engineer or a combination of both and the proposed construction is not so designed;

    (c)a person who prepared drawings, plans, specifications or other documents or gave an opinion concerning the compliance of the proposed building or construction with the building code does not have the applicable qualifications, if any, set out in the building code or does not have the insurance, if any, required by the building code;

    (d)the plans review certificate, if any, required for the application does not contain the prescribed information;

    (e)the application for the permit is not complete; or

    (f)any fees due have not been paid.

    (2.1)If the application includes a plans review certificate that contains the prescribed information, the chief building official is not entitled to refuse to issue the permit on the grounds that the proposed construction of the building to which the certificate relates does not comply with the building code.

    (2.2)If an application for a permit meets the requirements prescribed by regulation, the chief building official shall, unless the circumstances prescribed by regulation apply, decide within the period prescribed by regulation whether to issue the permit or to refuse to issue it.

    (2.3)If the chief building official refuses to issue the permit, he or she shall inform the applicant of all of the reasons for the refusal of the permit and shall do so within the period prescribed by regulation.

    (3)Even though all requirements have not been met to obtain a permit under subsection (2), the chief building official may issue a conditional permit for any stage of construction if,

    (a)compliance with by-laws passed under sections 34 and 38 of the Planning Act and with such other applicable law as may be set out in the building code has been achieved in respect of the proposed building or construction;

    (b)the chief building official is of the opinion that unreasonable delays in the construction would occur if a conditional permit is not granted; and

    (c)the applicant and such other person as the chief building official determines agree in writing with the municipality, upper-tier municipality, board of health, planning board, conservation authority or the Crown in right of Ontario to,

    (i)assume all risk in commencing the construction,

    (ii)obtain all necessary approvals in the time set out in the agreement or, if none, as soon as practicable,

    (iii)file plans and specifications of the complete building in the time set out in the agreement,

    (iv)at the applicant’s own expense, remove the building and restore the site in the manner specified in the agreement if approvals are not obtained or plans filed in the time set out in the agreement, and

    (v)comply with such other conditions as the chief building official considers necessary, including the provision of security for compliance with subclause (iv).

    (3.1)A principal authority may, in writing, delegate to the chief building official the power to enter into agreements described in clause (3) (c) and may impose conditions or restrictions with respect to the delegation.

    (4)In considering whether a conditional permit should be granted, the chief building official shall, among other matters, have regard to the potential difficulty in restoring the site to its original state and use if required approvals are not obtained.

    (5)Any agreement entered into under clause (3) (c) may be registered against the land to which it applies and the municipality, upper-tier municipality, board of health, planning board, conservation authority or the Province of Ontario, as the case may be, is entitled to enforce its provisions against the registered owner and, subject to the Registry Act and the Land Titles Act, any person acquiring any interest in the land subsequent to the registration of the agreement.

    (6)If the chief building official determines that a building has not been removed or a site restored as required by an agreement under clause (3) (c), the chief building official may cause the building to be removed and the site restored and for this purpose the chief building official, an inspector and their agents may enter upon the land and into the building governed by the agreement at any reasonable time without a warrant.

    (7)If the building is in a municipality, the municipality shall have a lien on the land for the amount spent on the removal of the building and restoration of the site under subsection (6) and the amount shall have priority lien status as described in section 1 of the Municipal Act, 2001 or section 3 of the City of Toronto Act, 2006, as the case may be.

    (8)If the building is in territory without municipal organization, the amount spent on the removal of the building and restoration of the site under subsection (6) is a debt owing to the Crown and may be collected under the Provincial Land Tax Act, 2006 as if it was tax imposed under that Act.

    (8.1)The chief building official shall, within the period and in the manner prescribed by regulation, give to the corporation designated under section 2 of the Ontario New Home Warranties Plan Act the information prescribed by regulation relating to permits issued under this section and the applications for those permits.

    (9)Upon reasonable grounds, the chief building official or registered code agency may refer drawings, plans or specifications accompanying applications for permits or the reports arising out of the general review of the construction of a building to the Association of Professional Engineers of Ontario or the Ontario Association of Architects for the purpose of determining if the Professional Engineers Act or the Architects Act is being contravened.

    (9.1)At the request of the Association of Professional Engineers of Ontario or the Ontario Association of Architects, the chief building official shall refer documents and information described in subsection (9) to those associations for the purpose of determining if the Professional Engineers Act or the Architects Act is being contravened.

    (10)Subject to section 25, the chief building official may revoke a permit issued under this Act,

    (a)if it was issued on mistaken, false or incorrect information;

    (b)if, after six months after its issuance, the construction or demolition in respect of which it was issued has not, in the opinion of the chief building official, been seriously commenced;

    (c)if the construction or demolition of the building is, in the opinion of the chief building official, substantially suspended or discontinued for a period of more than one year;

    (d)if it was issued in error;

    (e)if the holder requests in writing that it be revoked; or

    (f)if a term of the agreement under clause (3) (c) has not been complied with.

    (11)No person shall construct or demolish a building or cause a building to be constructed or demolished except in accordance with this Act and the building code.

    (12)No person shall make a material change or cause a material change to be made to a plan, specification, document or other information on the basis of which a permit was issued without notifying, filing details with and obtaining the authorization of the chief building official.

    (13)No person shall construct or demolish a building or cause a building to be constructed or demolished except in accordance with the plans, specifications, documents and any other information on the basis of which a permit was issued or any changes to them authorized by the chief building official.

    (14)If a request for authorization referred to in subsection (12) or (13) is accompanied by a change certificate that contains the prescribed information, the chief building official is not entitled to refuse to authorize the change on the grounds that the construction of the building to which the certificate relates does not comply with the building code.

    Open BCA s. 8 in the code viewer
  • BCA s. 10 Change of use

    (1)Even though no construction is proposed, no person shall change the use of a building or part of a building or permit the use to be changed if the change would result in an increase in hazard, as determined in accordance with the building code, unless a permit has been issued by the chief building official.

    (2)The chief building official shall issue a permit under subsection (1), unless,

    (a)the building if used as proposed would result in a contravention of this Act or the building code or any other applicable law;

    (b)the application for it is incomplete; or

    (c)any fees due are unpaid.

    Open BCA s. 10 in the code viewer
  • BCA s. 10.1 Prohibition re sewage systems

    No person shall operate or maintain a sewage system or permit a sewage system to be operated or maintained except in accordance with this Act and the building code.

    Open BCA s. 10.1 in the code viewer
  • BCA s. 10.2 Notice of readiness for inspection

    (1)At each stage of construction specified in the building code, the prescribed person shall notify the chief building official or the registered code agency, if any, that the construction is ready to be inspected.

    (2)After the notice is received, an inspector or the registered code agency, as the case may be, shall carry out the inspection required by the building code within the prescribed period.

    Open BCA s. 10.2 in the code viewer
  • OBC Div. C 1.3.5.3. Prescribed Inspections

    (1)Except as provided in Sentence (2), an inspector or registered code agency, as the case may be, shall, not later than two days after receipt of a notice given under Sentence 1.3.5.1.(2), undertake a site inspection of the building to which the notice relates.

    (2)Where a notice given under Sentence 1.3.5.1.(2) relates to matters described in Clause 1.3.5.1.(2)(l) or (m), an inspector or registered code agency, as the case may be, shall, not later than five days after receipt of the notice, undertake a site inspection of the sewage system to which the notice relates.

    (2.1)Where a notice given under Sentence 1.3.5.1.(2) relates to matters described in Clause 1.3.5.1.(2)(q), an inspector or registered code agency, as the case may be, shall, not later than ten days after receipt of the notice, undertake a site inspection of the building to which the notice relates.

    (3)When undertaking an inspection required under Sentence (1), (2) or (2.1), the inspector or registered code agency, as the case may be, may consider reports concerning whether the building or a part of the building complies with the Act or this Code.

    (4)For greater certainty, when undertaking an inspection required under Sentence (1), (2) or (2.1), the inspector or registered code agency, as the case may be, may choose to not attend at the physical site of the building and may instead undertake the inspection using other means.

    (5)The time periods referred to in Sentences (1), (2) and (2.1) shall begin on the day following the day on which the notice is given.

    (6)The time periods referred to in Sentences (1), (2) and (2.1) shall not include Saturdays, holidays and all other days when the offices of the principal authority are not open for the transaction of business with the public.

    Open OBC Div. C 1.3.5.3. in the code viewer
  • BCA s. 11 Occupancy or use after completion

    (1)Except as authorized by the building code, a person shall not occupy or use a building or part of a building that is newly erected or installed or permit it to be occupied or used until the requirements set out in this section are met.

    (2)Notice of the date of completion of the building or part must be given to the chief building official or the registered code agency, if any.

    (3)If a registered code agency has been appointed for the building or part of the building by a principal authority to perform the functions described in clause 4.1 (4) (b) or (c) or has been appointed under section 4.2, a final certificate that contains the prescribed information must be issued.

    (4)If subsection (3) does not apply,

    (a)either the building or part must be inspected or 10 days must elapse after notice of the date of completion is served on the chief building official; and

    (b)any order made under section 12 must be complied with.

    Open BCA s. 11 in the code viewer
  • BCA s. 12 Inspection of buildings and building sites

    (1)An inspector may enter upon land and into buildings at any reasonable time without a warrant for the purpose of inspecting the building or site to determine whether or not the following are being complied with:

    1. This Act.

    2. The building code.

    3. An order made under this Act.

    (2)An inspector who finds a contravention of this Act or the building code may make an order directing compliance with this Act or the building code and may require the order to be carried out immediately or within such time as is specified in the order.

    (3)The order shall be served on the person whom the inspector believes is contravening this Act or the building code.

    (4)The prescribed form or the form approved by the Minister must be used for the order and it must contain sufficient information to specify the nature of the contravention and its location and the nature of the compliance that is required.

    (5)A copy of an order made under subsection (2) may be,

    (a)posted on the site of the construction or demolition in a location visible to the public;

    (b)made available to the public by,

    (i)posting the copy of the order on the website of the principal authority, or

    (ii)allowing members of the public, during normal business hours, to inspect and copy the order at their own expense; and

    (c)registered in the proper land registry office.

    (6)If an order made under subsection (2) is registered in the proper land registry office, any person acquiring any interest in the land subsequent to the registration of the order shall be deemed to have been served with the order on the day on which the order was served.

    (7)When the requirements of an order described in subsection (6) have been satisfied, the chief building official shall register in the proper land registry office a certificate that such requirements have been satisfied, which shall operate as a discharge of the order.

    (8)In the case of an order that has been made available to the public in accordance with clause (5) (b), when the requirements of the order have been satisfied, an inspector shall indicate on the copy of the order, or by such other means as may be prescribed by regulation, that the requirements of the order have been satisfied.

    Open BCA s. 12 in the code viewer
  • BCA s. 13 Order not to cover

    (1)An inspector may make an order prohibiting the covering or enclosing of any part of a building pending inspection.

    (1.1)The prescribed form or the form approved by the Minister must be used for an order made under this section.

    (2)The order shall be served on the person to whom the permit is issued, if any, and on such other persons affected thereby as the inspector determines.

    (3)A copy of an order made under this section may be,

    (a)posted on the site of the construction or demolition in a location visible to the public;

    (b)made available to the public by,

    (i)posting the copy of the order on the website of the principal authority, or

    (ii)allowing members of the public, during normal business hours, to inspect and copy the order at their own expense; and

    (c)registered in the proper land registry office.

    (3.1)If an order made under this section is registered in the proper land registry office, any person acquiring any interest in the land subsequent to the registration of the order shall be deemed to have been served with the order on the day on which the order was served.

    (3.2)When the requirements of an order described in subsection (3.1) have been satisfied, the chief building official shall register in the proper land registry office a certificate that such requirements have been satisfied, which shall operate as a discharge of the order.

    (3.3)In the case of an order that has been made available to the public in accordance with clause (3) (b), when the requirements of the order have been satisfied, an inspector shall indicate on the copy of the order, or by such other means as may be prescribed by regulation, that the requirements of the order have been satisfied.

    (4)An inspection shall be made within a reasonable time after the person to whom the order is made has given notice that the part of the building is ready for inspection.

    (5)Section 27 does not apply to a notice under subsection (4).

    (6)A chief building official or registered code agency who has reason to believe that part of a building that is covered or enclosed has not been constructed in compliance with this Act or the building code may order the persons responsible for the construction to uncover the part at their own expense for the purpose of an inspection if,

    (a)the part was covered or enclosed contrary to an order made under subsection (1);

    (b)a notice required to be given to the chief building official, registered code agency or inspector before the part was covered or enclosed under a by-law, resolution or regulation made under clause 7 (e) was not given, or a notice required under section 10.2 was not received;

    (c)in cases where a notice required under section 10.2 is received, the period prescribed under subsection 10.2 (2) did not elapse before the part was covered or enclosed;

    (d)in cases where a notice required by a by-law, resolution or regulation made under clause 7 (e) is given,

    (i)the inspection period prescribed under clause 7 (e) did not elapse before the part was covered or enclosed, or

    (ii)if an inspection period is not prescribed under clause 7 (e), a reasonable period of time after the notice was given did not elapse before the part was covered or enclosed; or

    (e)the part has been constructed without a permit being issued.

    Open BCA s. 13 in the code viewer
Show all 9 articles
  • BCA s. 14 Stop work order

    (1)If an order made under section 12 or 13 is not complied with within the time specified in it, or where no time is specified, within a reasonable time, the chief building official or registered code agency, as the case may be, may order that all or any part of the construction or demolition cease.

    (1.1)The prescribed form or the form approved by the Minister must be used for the order.

    (2)The order shall be served on such persons affected thereby as the chief building official or registered code agency determines and a copy shall be posted on the site of the construction or demolition in a location visible to the public.

    (3)The order is effective from the time it is posted under subsection (2).

    (3.1)A copy of an order made under subsection (1) may be,

    (a)made available to the public by,

    (i)posting the copy of the order on the website of the principal authority, or

    (ii)allowing members of the public, during normal business hours, to inspect and copy the order at their own expense; and

    (b)registered in the proper land registry office.

    (3.2)If an order made under subsection (1) is registered in the proper land registry office, any person acquiring any interest in the land subsequent to the registration of the order shall be deemed to have been served with the order on the day on which the order was served.

    (3.3)When the requirements of an order described in subsection (3.2) have been satisfied, the chief building official shall register in the proper land registry office a certificate that such requirements have been satisfied, which shall operate as a discharge of the order.

    (3.4)In the case of an order that has been made available to the public in accordance with clause (3.1) (a), when the requirements of the order have been satisfied, an inspector shall indicate on the copy of the order, or by such other means as may be prescribed by regulation, that the requirements of the order have been satisfied.

    (4)If an order to cease construction or demolition is made, no person shall perform any act in the construction or demolition of the building in respect of which the order is made other than work necessary to carry out the order made under section 12 or 13.

    (5)When a registered code agency makes an order under this section, the agency shall refer the matter to the chief building official as soon as practicable.

    (6)The referral must be made in the prescribed manner.

    (7)After making the referral, the registered code agency shall take no further steps in respect of the matter to which the order refers and the principal authority that issued the permit is responsible for the enforcement of this Act in respect of the matter.

    (8)The chief building official may amend or rescind any order made by the registered code agency in respect of the matter.

    Open BCA s. 14 in the code viewer