Values this chapter turns on

to decide a complete Part 3 permit application
20 days
to decide a complete Part 3 permit application
to inspect after a sewage system notice
5 days
to inspect after a sewage system notice
to send Tarion permit information
45 days
to send Tarion permit information
max area of a house built off site under 1.11.
37 m²
max area of a house built off site under 1.11.

Division C Part 1 turns the Act's "as prescribed" into numbers and lists. A chief building official is tested on all of it: when an architect or engineer must design or review, who may apply, how many days the CBO has to decide, when a conditional permit is barred, what occupancy before completion requires, which notices trigger inspections and how fast, who the "designated persons" are, and how fees are changed. Chapter 4 covers Section 1.10 (maintenance programs) and chapter 7 covers Section 1.4 (warrant forms).

Application, design and general review

Part 1 applies to all buildings and the code is administered in conformance with the Act (OBC Div. C 1.1.1.2.OBC Div. C 1.1.1.2. Conformance with Administrative Requirements(1) This Code shall be administered in conformance with the Act.).

Engineer design is required for foundations below an adjacent building's footings within the soil's angle of repose, underpinning, sprinkler-protected glazed walls, shelf and rack storage, tent framing over 225 m², and some signs (OBC Div. C 1.2.1.2.OBC Div. C 1.2.1.2. Design by Architect or Professional Engineer(1) A foundation of a building shall be designed by a professional engineer where, (a) the foundation is to be constructed below the level of the footings of an adjacent building and within the angle of repose of the soil, as drawn from the bottom of the footings, or (b) underpinning of a foundation is to be…).

General review by an architect, engineer or both follows Table 1.2.2.1., keyed to major occupancy, mostly with 600 m² gross area and 3 storey thresholds; assembly, care, treatment, detention and retirement homes need review for every building (OBC Div. C 1.2.2.1.OBC Div. C 1.2.2.1. General Review by Architect or Professional Engineer(1) The construction, including, for greater certainty, enlargement or alteration, of every building or part of it described in Table 1.2.2.1. shall be reviewed by an architect or a professional engineer or a combination of both as set out in Column 3 of the Table. (2) A person who intends to construct or have…). Reviewers forward written reports to the CBO or RCA. Only an architect may review a building built to an architect's design, and only an engineer one built to an engineer's design (OBC Div. C 1.2.2.2.OBC Div. C 1.2.2.2. Restriction for General Review(1) Only an architect may carry out or provide the general review of the construction of a building, (a) that is constructed in accordance with a design prepared or provided by an architect, or (b) in relation to services that are provided by an architect in connection with the design in accordance with which the…).

Demolition needs an engineer's general review if the building exceeds 3 storeys or 600 m² building area, has pre- or post-tensioned members, digs below adjacent footings within the angle of repose, or uses explosives or a laser (OBC Div. C 1.2.2.3.OBC Div. C 1.2.2.3. Demolition of a Building(1) The applicant for a permit respecting the demolition of a building shall retain a professional engineer to undertake the general review of the project during demolition, where, (a) the building exceeds 3 storeys in building height or 600 m² in building area, (b) the building structure includes pre-tensioned or…).

Practice this topic

Permits, applications, timelines and conditional permits

Exemptions from a s. 8 permit include demolition of a farm building on a farm, work in territory without municipal organization (except sewage systems), Class 1 sewage systems, tents up to 60 m² aggregate meeting conditions, and sheds up to 15 m² meeting conditions (OBC Div. C 1.3.1.1.OBC Div. C 1.3.1.1. Requirement for Permits(1) A person is exempt from the requirement to obtain a permit under section 8 of the Act, (a) for the demolition of a farm building located on a farm, (b) subject to Sentence (2), for the construction or demolition of a building in territory without municipal organization, or (c) for the construction of a Class 1…). Demolition may not start until occupants leave unless their safety is not affected.

The applicant is the owner (including registered owner, lessee and mortgagee in possession) or the owner's authorized agent, on the Minister's form (OBC Div. C 1.3.1.2.OBC Div. C 1.3.1.2. Applications for Permits under Section 8 of the Act(1) An application for a permit under section 8 of the Act to construct or demolish a building shall be made by, (a) the owner of the property on which the proposed construction or demolition is to take place, or (b) the authorized agent of the owner referred to in Clause (a). (2) An application referred to in…).

Decision periods (OBC Div. C 1.3.1.3.OBC Div. C 1.3.1.3. Period Within Which a Permit is Issued or Refused(1) Subject to Sentences (2) and (3) and unless the circumstances set out in Sentence (6) exist, if an application for a permit under subsection 8(1) of the Act that meets the requirements of Sentence (5) is submitted to a chief building official, the chief building official shall, within the time period set out in…, Table 1.3.1.3.OBC Div. C Table 1.3.1.3. Period Within Which Permit Shall be Issued or Refused — Forming Part of Article 1.3.1.3.Table 1.3.1.3. Period Within Which Permit Shall be Issued or Refused — Forming Part of Article 1.3.1.3. Item | Class of Building | Time Period 1 | (a) Except for a retirement home, a house where no dwelling unit is located above another dwelling unit. (b) A detached structure that serves a building described in Clause…). For an application meeting Sentence (5), the CBO must issue the permit or refuse it with written reasons within:

Class Days
Houses with no unit above another (not retirement homes), small detached structures up to 55 m² serving them, tents, signs, demountable stages 10
Other Part 9 buildings, farm buildings up to 600 m² 15
Part 3 buildings, farm buildings over 600 m², retirement homes 20
Post-disaster buildings, high buildings (3.2.6.) and 3.2.8.3. to 3.2.8.8. buildings 30

Counting rules: the period starts the day after a compliant application; Saturdays, holidays and days the office is closed are excluded. Mixed classes take the longer period. Small plumbing structures, outside plumbing, sewage systems and designated structures get the longer of 10 days and the period of the building served. Where another body enforces sewage systems, the clock starts after the later of the application date and the sewage permit issue date. The CBO is released from the deadline if, within two days, the CBO determines that plans or documents are missing or the work will contravene applicable law and gives written reasons.

Sentence (5) requires the approved form, an eligible applicant, completed fields and schedules, fees paid, and a written declaration covering completeness and compliance with applicable law.

Change of use (OBC Div. C 1.3.1.4.OBC Div. C 1.3.1.4. Permits Under Section 10 of the Act(1) Except as provided in Sentence (2), the following changes in use of a building or part of a building constitute an increase in hazard for the purposes of section 10 of the Act and require a permit under section 10 of the Act: (a) a change of the major occupancy of all or part of a building that is designated with…): an increase in hazard includes "Y" changes in Table 1.3.1.4., one Group C suite becoming several, assembly to gaming premises, farm building changes, changes to post-disaster buildings or retirement homes, and unknown prior occupancy. No s. 10 permit is needed if a s. 8 permit covers the work, or in unorganized territory.

Conditional permits (OBC Div. C 1.3.1.5.OBC Div. C 1.3.1.5. Conditional Permits(1) The chief building official shall not issue a conditional permit for any stage of construction under subsection 8(3) of the Act unless compliance with the following applicable laws has been achieved in respect of the proposed building or construction: (a) section 3 of the Building Transit Faster Act, 2020 with…): the CBO may not issue one unless listed laws are complied with (Conservation Authorities Act permits, Environmental Assessment Act approvals, Niagara Escarpment, Ontario Heritage Act consents, condominium conversion confirmations). The zoning condition is waived where a committee of adjustment's minor variances, with no objections, achieve full compliance, or where the work is needed to comply with a Fire Code order or a s. 15.9(4) unsafe order. The permit must show it is conditional.

The CBO gives Tarion permit information for new Group C buildings (not boarding houses or hotels, not alterations) within 45 days (OBC Div. C 1.3.1.6.OBC Div. C 1.3.1.6. Information to be Given to Tarion Warranty Corporation(1) This Article prescribes, for the purposes of subsection 8(8.1) of the Act, the information relating to permits issued under section 8 of the Act and the applications for those permits that the chief building official is required to give to Tarion Warranty Corporation and the time within which the information is…), and gives the fire chief (or clerk) information on lightweight floor and roof systems in non-house buildings within 45 days (OBC Div. C 1.3.1.7.OBC Div. C 1.3.1.7. Information to be Given to the Fire Chief or Clerk(1) This Article applies to buildings, (a) constructed using, (i) lightweight pre-engineered floor or roof systems containing lightweight elements such as wood I-joists, cold-formed steel joists, wood truss assemblies with metal or wood plates and metal web wood joists, or (ii) lightweight floor or roof systems…).

Practice this topic

Site documents, occupancy and fire department approval

The permit or a copy must be posted in a conspicuous place on the property during construction or demolition (OBC Div. C 1.3.2.1.OBC Div. C 1.3.2.1. Permit Posting(1) Where a permit has been issued pursuant to the Act, the person to whom it is issued shall have the permit or a copy of it posted at all times during construction or demolition in a conspicuous place on the property in respect of which the permit was issued.); the site must keep certified drawings, BMEC authorizations and Minister's rulings (OBC Div. C 1.3.2.2.OBC Div. C 1.3.2.2. Documentation on Site(1) The person in charge of the construction of the building shall keep and maintain on the site of the construction, (a) at least one copy of drawings and specifications certified by the chief building official or a person designated by the chief building official to be a copy of those submitted with the application…).

Occupancy before completion: a CBO-issued permit after a long checklist (structure and walls to the roof, fire separations, exits, fire protection systems, sewage system working) (OBC Div. C 1.3.3.1.OBC Div. C 1.3.3.1. Occupancy Permit — General(1) Except as permitted in Sentence 1.3.3.2.(1), a person may occupy or permit to be occupied any building or part of it that has not been fully completed at the date of occupation where the chief building official or a person designated by the chief building official has issued a permit authorizing occupation of the…), or without a permit for small residential buildings that meet 1.3.3.2. Separate permit regimes apply to houses with no shared egress (1.3.3.4.), buildings within the scope of Division B 3.2.2.51. or 3.2.2.60. (1.3.3.5.), super tall buildings of 65 or more storeys or more than 250 m in height (1.3.3.7.) and deferred development charges (1.3.3.8.). Where an RCA handles post-permit work, the CBO issues the occupancy permit after the RCA's certificate.

If council assigns fire safety enforcement to the fire chief as an inspector, the CBO may not issue the permit until the fire chief approves the drawings, unless an RCA has been appointed for plans review (OBC Div. C 1.3.4.1.OBC Div. C 1.3.4.1. Fire Department Approval(1) Subject to Sentence (2), if the council of a municipality assigns specific responsibility for the enforcement of any portion of this Code respecting fire safety matters to an inspector who is the chief of the fire department of the municipality, the chief building official shall not issue a permit to construct a…).

Practice this topic

Prescribed notices, inspections and as constructed plans

The permit holder notifies the CBO or RCA at the stages in OBC Div. C 1.3.5.1.OBC Div. C 1.3.5.1. Prescribed Notices(1) This Article sets out the notices that are required under section 10.2 of the Act. (2) The person to whom a permit under section 8 of the Act is issued shall notify the chief building official or, where a registered code agency is appointed under the Act in respect of the construction to which the notice relates… (footings, foundations before backfill, framing, insulation, air barrier, fire separations and protection systems, plumbing tests, sewage system stages, occupancy). By-laws may add stages such as commencement, cladding, grading and as constructed drawings (OBC Div. C 1.3.5.2.OBC Div. C 1.3.5.2. Additional Notices(1) A by-law, resolution or regulation made by a principal authority under clause 7(1)(e) of the Act may require that notice of one or more of the following stages of construction be given by the person to whom a permit is issued under section 8 of the Act: (a) commencement of construction of the building, (b)…).

Notice Inspection deadline
General prescribed notices 2 days
Readiness to construct, or completion before backfill of, a sewage system 5 days
Deferred development charge occupancy 10 days

Days start the next day and exclude Saturdays, holidays and closed days; remote inspection is allowed (OBC Div. C 1.3.5.3.OBC Div. C 1.3.5.3. Prescribed Inspections(1) Except as provided in Sentence (2), an inspector or registered code agency, as the case may be, shall, not later than two days after receipt of a notice given under Sentence 1.3.5.1.(2), undertake a site inspection of the building to which the notice relates. (2) Where a notice given under Sentence 1.3.5.1.(2)…). Where a by-law under clause 7(1)(g) exists, the CBO may require as constructed plans (OBC Div. C 1.3.6.1.OBC Div. C 1.3.6.1. Application(1) Where a by-law, resolution or regulation has been made by a principal authority under clause 7(1)(g) of the Act, the chief building official may require that as constructed plans for the whole of, or any part or system of, a building or any class of buildings be provided by the persons responsible for the…).

Practice this topic

Designated persons and prescribed persons

The director and designated Ministry staff enforce qualification requirements for CBOs, inspectors, RCAs, designers and sewage businesses (OBC Div. C 1.5.1.1.OBC Div. C 1.5.1.1. General(1) The director and employees in the Ministry of Municipal Affairs and Housing who work under the supervision of the director and are specified by the director are designated for the purposes of the enforcement of the Act and this Code in relation to the qualifications of, (a) chief building officials, (b)…). The director may certify records under s. 37(2) and apply for s. 38 orders; designated staff may enter under s. 12(1) (subject to s. 16) and use s. 18 powers. The director is the prescribed person for licence suspension under s. 38.1 (OBC Div. C 1.6.1.1.OBC Div. C 1.6.1.1. General(1) The director is prescribed for the purposes of section 38.1 of the Act.).

Practice this topic

Sewage enforcement, language and fees

Table 1.7.1.1. names the boards of health and conservation authority that enforce sewage provisions (OBC Div. C 1.7.1.1.OBC Div. C 1.7.1.1. General(1) The boards of health and conservation authorities listed in Column 1 of Table 1.7.1.1. are prescribed, for the purposes of subsection 3.1(1) of the Act, as the boards of health and conservation authorities that are responsible for the enforcement of the provisions of the Act and this Code related to sewage systems…). Required signs are in English, or English and French (OBC Div. C 1.8.1.1.OBC Div. C 1.8.1.1. Language Used on Required Signs(1) All required signs in this Code shall be displayed in the English language or in the English and French languages, including operational material on all life safety equipment and devices.).

The annual fee report covers fees collected and direct and indirect costs for a 12-month period ending no earlier than three months before release, plus any reserve fund (OBC Div. C 1.9.1.1.OBC Div. C 1.9.1.1. Annual Report(1) The report referred to in subsection 7(4) of the Act shall contain the following information in respect of fees authorized under clause 7(1)(c) of the Act: (a) total fees collected in the 12-month period ending no earlier than three months before the release of the report, (b) the direct and indirect costs of…). Before changing permit or maintenance inspection fees, the principal authority holds a public meeting with at least 21 days' notice and publishes the cost estimate, the fee change and its rationale (OBC Div. C 1.9.1.2.OBC Div. C 1.9.1.2. Change of Fees(1) Before passing a by-law or resolution or making a regulation under clause 7(1)(c) of the Act to introduce or change a fee imposed for applications for a permit, for the issuance of a permit or for a maintenance inspection, a principal authority shall, (a) hold the public meeting required under subsection 7(6) of…).

Practice this topic

Tiny houses and off-site construction

Section 1.11 covers houses of one dwelling unit, 37 m² or less, partly built in one place and moved unoccupied (OBC Div. C 1.11.1.1.OBC Div. C 1.11.1.1. Scope(1) This Section applies to houses that, (a) have not more than one dwelling unit, (b) are 37 m² or less in building area, and (c) are to be, (i) partially constructed in one municipality and moved to be installed at a location in another municipality without having been previously occupied, or (ii) partially…). The building municipality's permit skips applicable law and site installation items; a second permit is needed where the house is installed (OBC Div. C 1.11.1.2.OBC Div. C 1.11.1.2. Permits(1) Provided the conditions described in Sentence (2) are complied with, if an applicant for a permit under section 8 of the Act makes an application to the chief building official of the municipality in which a house is to be partially constructed but not installed, the applicant is exempt from demonstrating…), and the first CBO gives a letter of compliance (OBC Div. C 1.11.1.3.OBC Div. C 1.11.1.3. Inspections(1) Where a permit is applied for as described in Sentence 1.11.1.2.(1) or (5), the person to whom a permit under section 8 of the Act is issued shall give notice as described in Articles 1.3.5.1. and 1.3.5.2. to the chief building official or registered code agency, as the case may be, of the municipality who issued…). Part 3 factory-built components certified to CSA A277 are deemed to comply, except off-factory components and site installation (OBC Div. C 1.12.1.1.OBC Div. C 1.12.1.1. Certification and Compliance(1) Except as provided in Sentence (2), a manufactured building or a manufactured part of a building within the scope of Part 3 is deemed to comply with this Code if it is certified in accordance with CSA A277, “Procedure for Certification of Prefabricated Buildings, Modules, and Panels.” (2) The requirements of this…).

Practice this topic

Worked scenario and traps

A complete application for a 3-storey apartment building of 1,200 m² arrives Tuesday; offices are open weekdays with no holidays. It is a Part 3 building: 20 days, starting Wednesday, so the decision is due four weeks later on Tuesday.

  • Business days, not calendar days.
  • Two days to flag missing documents, not ten.
  • Sewage system inspections: five days.

Chapter review

Chapter at a glance

One line per section: the idea to carry into the exam. Then the answers that most often catch candidates out.

Practice this chapter

Questions on Division C Part 1 in full, in the exam format, every answer explained and cited to its article. Sign in to start; a free account gets the free questions.

Code cited in this chapter

Based on the official 2024 Building Code Compendium on ontario.ca.

© King's Printer for Ontario, 2024. Reproduced with permission.

  • OBC Div. C 1.1.1.2. Conformance with Administrative Requirements

    (1)This Code shall be administered in conformance with the Act.

    Open OBC Div. C 1.1.1.2. in the code viewer
  • OBC Div. C 1.2.1.2. Design by Architect or Professional Engineer

    (1)A foundation of a building shall be designed by a professional engineer where,

    (a)the foundation is to be constructed below the level of the footings of an adjacent building and within the angle of repose of the soil, as drawn from the bottom of the footings, or

    (b)underpinning of a foundation is to be undertaken.

    (2)A sprinkler protected glazed wall assembly described in Article 3.1.8.20. of Division B shall be designed by a professional engineer.

    (3)A shelf and rack storage system described in Section 3.16. of Division B shall be designed by a professional engineer.

    (4)The time-based egress analysis for a shelf and rack storage system described in Sentence 3.16.1.7.(7) of Division B shall be prepared or provided by an architect or a professional engineer or a combination of both.

    (5)The supporting framing structure and anchorage system for a tent occupying an area greater than 225 m² shall be designed by a professional engineer.

    (6)A sign structure attached in any manner to a building shall be designed by an architect or a professional engineer or a combination of both where it is,

    (a)a projecting sign that weighs more than 115 kg, or

    (b)a roof sign that has any face that is more than 10 m².

    (7)A projecting sign attached in any manner to a parapet wall shall be designed by an architect or a professional engineer or a combination of both.

    Open OBC Div. C 1.2.1.2. in the code viewer
  • OBC Div. C 1.2.2.1. General Review by Architect or Professional Engineer

    (1)The construction, including, for greater certainty, enlargement or alteration, of every building or part of it described in Table 1.2.2.1. shall be reviewed by an architect or a professional engineer or a combination of both as set out in Column 3 of the Table.

    (2)A person who intends to construct or have constructed a building or part of it required by Sentences (1) and (4) to (9) to be reviewed by an architect or a professional engineer or a combination of both, shall ensure that an architect, professional engineer or both are retained to undertake the general review of the construction of the building in accordance with the performance standards of the Ontario Association of Architects or the Association of Professional Engineers of Ontario, as applicable, to determine whether the construction is in general conformity with the plans, sketches, drawings, graphic representations, specifications and other documents that form the basis for the issuance of a permit under section 8 of the Act or any changes to it authorized by the chief building official.

    (3)The architect, professional engineer or both who have been retained to undertake the general review of the construction of a building, shall forward copies of written reports arising out of the general review to the chief building official or registered code agency, as the case may be.

    (4)The construction of a foundation of a building shall be reviewed by a professional engineer where,

    (a)the foundation is to be constructed below the level of the footings of an adjacent building and within the angle of repose of the soil, as drawn from the bottom of the footings, or

    (b)underpinning of a foundation is to be undertaken.

    (5)The construction of a sprinkler protected glazed wall assembly described in Article 3.1.8.20. of Division B shall be reviewed by a professional engineer.

    (6)The construction of a shelf and rack storage system described in Section 3.16. of Division B shall be reviewed by a professional engineer.

    (7)The construction of a supporting framing structure and anchorage system for a tent occupying an area greater than 225 m² shall be reviewed by a professional engineer.

    (8)The construction of a sign structure shall be reviewed by an architect or a professional engineer or a combination of both, where the sign is,

    (a)a ground sign that exceeds 7.5 m in height above the adjacent finished ground,

    (b)a projecting sign that weighs more than 115 kg, or

    (c)a roof sign that has any face that is more than 10 m².

    (9)The construction of a projecting sign attached in any manner to a parapet wall shall be reviewed by an architect, professional engineer or a combination of both.

    (10)The construction of a demountable stage or demountable support structure regulated by Section 3.17. of Division B shall be reviewed by a professional engineer.

    Open OBC Div. C 1.2.2.1. in the code viewer
  • OBC Div. C 1.2.2.2. Restriction for General Review

    (1)Only an architect may carry out or provide the general review of the construction of a building,

    (a)that is constructed in accordance with a design prepared or provided by an architect, or

    (b)in relation to services that are provided by an architect in connection with the design in accordance with which the building is constructed.

    (2)Only a professional engineer may carry out or provide the general review of the construction of a building,

    (a)that is constructed in accordance with a design prepared or provided by a professional engineer, or

    (b)in relation to services that are provided by a professional engineer in connection with the design in accordance with which the building is constructed.

    Open OBC Div. C 1.2.2.2. in the code viewer
  • OBC Div. C 1.2.2.3. Demolition of a Building

    (1)The applicant for a permit respecting the demolition of a building shall retain a professional engineer to undertake the general review of the project during demolition, where,

    (a)the building exceeds 3 storeys in building height or 600 m² in building area,

    (b)the building structure includes pre-tensioned or post-tensioned members,

    (c)it is proposed that the demolition will extend below the level of the footings of any adjacent building and occur within the angle of repose of the soil, as drawn from the bottom of such footings, or

    (d)explosives or a laser are to be used during the course of demolition.

    Open OBC Div. C 1.2.2.3. in the code viewer
  • OBC Div. C 1.3.1.1. Requirement for Permits

    (1)A person is exempt from the requirement to obtain a permit under section 8 of the Act,

    (a)for the demolition of a farm building located on a farm,

    (b)subject to Sentence (2), for the construction or demolition of a building in territory without municipal organization, or

    (c)for the construction of a Class 1 sewage system.

    (2)The exemption in Clause (1)(b) from the requirement to obtain a permit does not apply to the construction of a sewage system in territory without municipal organization.

    (3)The application for a permit respecting the demolition of a building to which Sentence 1.2.2.3.(1) applies shall include descriptions of the structural design characteristics of the building and the method of demolition of the building.

    (4)No person shall commence demolition of a building or any part of a building before the building has been vacated by the occupants except where the safety of the occupants is not affected.

    (5)A tent or group of tents is exempt from the requirement to obtain a permit under section 8 of the Act and is exempt from compliance with the Code provided that the tent or group of tents are,

    (a)not more than 60 m² in aggregate ground area,

    (b)not attached to a building, and

    (c)constructed more than 3 m from other structures.

    (6)A shed is exempt from the requirement to obtain a permit under section 8 of the Act and is exempt from compliance with this Code, provided that the shed,

    (a)is not more than 15 m² in gross area,

    (b)is not more than one storey in building height,

    (c)is not attached to a building or any other structure,

    (d)is used only for storage purposes ancillary to a principal building on the lot, and

    (e)does not have plumbing.

    (7)A demountable stage or demountable support structure not regulated by Section 3.17. of Division B is exempt from the requirement to obtain a permit under section 8 of the Act and is exempt from compliance with this Code.

    Open OBC Div. C 1.3.1.1. in the code viewer
  • OBC Div. C 1.3.1.2. Applications for Permits under Section 8 of the Act

    (1)An application for a permit under section 8 of the Act to construct or demolish a building shall be made by,

    (a)the owner of the property on which the proposed construction or demolition is to take place, or

    (b)the authorized agent of the owner referred to in Clause (a).

    (2)An application referred to in Sentence (1) shall be in a form approved by the Minister.

    (3)In Sentence (1), “owner” includes, in respect of the property on which the construction or demolition will take place, the registered owner, a lessee and a mortgagee in possession.

    Open OBC Div. C 1.3.1.2. in the code viewer
  • OBC Div. C 1.3.1.3. Period Within Which a Permit is Issued or Refused

    (1)Subject to Sentences (2) and (3) and unless the circumstances set out in Sentence (6) exist, if an application for a permit under subsection 8(1) of the Act that meets the requirements of Sentence (5) is submitted to a chief building official, the chief building official shall, within the time period set out in Column 2 of Table 1.3.1.3. corresponding to the class of building described in Column 1 of Table 1.3.1.3. for which the application is made,

    (a)issue the permit, or

    (b)refuse to issue the permit and provide in writing all of the reasons for the refusal.

    (2)If an application for a permit under subsection 8(1) of the Act proposes construction or demolition of two or more buildings of different classes described in Column 1 of Table 1.3.1.3. that have different time periods in Column 2 of Table 1.3.1.3., the longer of the time periods shall be the time period for the purposes of Sentence (1).

    (3)If an application for a permit under subsection 8(1) of the Act proposes construction or demolition of a building described in Sentence (4), the time period for the purposes of Sentence (1) shall be the longer of,

    (a)10 days, and

    (b)the time period corresponding to the class of the building described in Column 1 of Table 1.3.1.3. that the building described in Sentence (4) serves, if any.

    (4)A building referred to in Sentence (3) is,

    (a)a structure occupying an area of 10 m² or less that contains plumbing, including the plumbing appurtenant to it,

    (b)plumbing not located in a structure,

    (c)a sewage system, or

    (d)a structure designated in Article 1.3.3.5. of Division A.

    (5)The requirements that an application for a permit under subsection 8(1) of the Act must meet for the purposes of Sentence (1) are,

    (a)that the application is made in the form described in Sentence 1.3.1.2.(2),

    (b)that the applicant for the permit is a person described in Clause 1.3.1.2.(1)(a) or (b),

    (c)that all applicable fields on the application form and required schedules are completed,

    (d)that all required schedules are submitted with the application,

    (e)that payment is made of all fees that are required, under the applicable by-law, resolution or regulation made under clause 7(1)(c) of the Act, to be paid when the application is made, and

    (f)that the applicant has declared in writing that,

    (i)the application meets all the requirements set out in Clauses (a) to (e),

    (ii)the application is accompanied by the plans and specifications prescribed by the applicable by-law, resolution or regulation made under clause 7(1)(b) of the Act,

    (iii)the application is accompanied by the information and documents prescribed by the applicable by-law, resolution or regulation made under clause 7(1)(b) of the Act which enable the chief building official to determine whether the proposed building, construction or demolition will contravene any applicable law, and

    (iv)the proposed building, construction or demolition will not contravene any applicable law.

    (6)The chief building official is not required to make a decision within the time period required by Sentence (1) with respect to an application that meets the requirements of Sentence (5) if the chief building official,

    (a)determines that,

    (i)the application is not accompanied by the plans, specifications, information and documents referred to in Subclauses (5)(f)(ii) and (iii), or

    (ii)the proposed building, construction or demolition will contravene any applicable law, and

    (b)advises the applicant of his or her determination and provides in writing the reasons for the determination within two days.

    (7)Subject to Sentences (9) and (10), the time period described in Sentences (1) to (3) and in Clause (6)(b) shall begin on the day following the day on which an application that meets the requirements of Sentence (5) is submitted to the chief building official.

    (8)The time periods described in Column 2 of Table 1.3.1.3. and in Clause (6)(b) shall not include Saturdays, holidays and all other days when the offices of the principal authority are not open for the transaction of business with the public.

    (9)The time period in Sentence (10) applies where,

    (a)an application is made for the construction of a building that is served by a sewage system,

    (b)construction is proposed in respect of the sewage system that serves the building, and

    (c)a board of health, conservation authority, planning board or the council of an upper-tier municipality is responsible for the enforcement of the provisions of the Act and this Code related to the sewage system under section 3.1 of the Act or pursuant to an agreement under section 6.2 of the Act.

    (10)The time period described in Sentences (1) to (3) and in Clause (6)(b) for an application referred to in Clause (9)(a) shall begin on the day following the later of,

    (a)the day on which an application that meets the requirements of Sentence (5) is submitted to the chief building official, and

    (b)the day on which a permit for the construction of the sewage system referred to in Clause (9)(b) is issued.

    Open OBC Div. C 1.3.1.3. in the code viewer
Show all 31 articles
  • OBC Div. C Table 1.3.1.3. Period Within Which Permit Shall be Issued or Refused — Forming Part of Article 1.3.1.3.

    Table 1.3.1.3. Period Within Which Permit Shall be Issued or Refused — Forming Part of Article 1.3.1.3. Item | Class of Building | Time Period 1 | (a) Except for a retirement home, a house where no dwelling unit is located above another dwelling unit. (b) A detached structure that serves a building described in Clause (a) and does not exceed 55 m² in building area. (c) A tent to which Section 3.14. of Division B applies. (d) A sign to which Section 3.15. of Division B applies. (e) A demountable stage or demountable support structure to which Section 3.17. of Division B applies. | 10 days 2 | (a) Buildings described in Clause 1.3.3.3.(1)(a), (b) or (c) of Division A, other than buildings described in Column 1 of any of Items 1 and 4 of this Table. (b) Farm buildings that do not exceed 600 m² in building area. | 15 days 3 | (a) Buildings described in Sentence 1.3.3.2.(1) of Division A, other than buildings described in Column 1 of any of Items 1 and 4 of this Table. (b) Farm buildings exceeding 600 m² in building area. (c) Retirement homes. | 20 days 4 | (a) Post-disaster buildings. (b) Buildings to which Subsection 3.2.6. of Division B or any provision in Articles 3.2.8.3. to 3.2.8.8. of Division B applies. | 30 days N/A | Column 1 | Column 2

    Open OBC Div. C Table 1.3.1.3. in the code viewer
  • OBC Div. C 1.3.1.4. Permits Under Section 10 of the Act

    (1)Except as provided in Sentence (2), the following changes in use of a building or part of a building constitute an increase in hazard for the purposes of section 10 of the Act and require a permit under section 10 of the Act:

    (a)a change of the major occupancy of all or part of a building that is designated with a “Y” in Table 1.3.1.4. takes place,

    (b)a suite of a Group C major occupancy is converted into more than one suite of Group C major occupancy,

    (c)a suite or part of a suite of a Group A, Division 2 or a Group A, Division 4 major occupancy is converted to a gaming premises,

    (d)a farm building or part of a farm building is changed to another major occupancy other than a Group G major occupancy,

    (e)a farm building or part of a farm building is changed to a Group G, Division 1 major occupancy.

    (f)a building or part of a building is changed to a post-disaster building,

    (g)a building or part of a building is changed to a retirement home, or

    (h)the use of a building or part of a building is changed and the previous major occupancy of the building or part of the building cannot be determined.

    (2)A person is exempt from the requirement to obtain a permit under section 10 of the Act where the change in use of the building or part of the building will result from proposed construction and a permit under section 8 of the Act has been issued in respect of such construction.

    (3)A person is exempt from the requirement to obtain a permit under section 10 of the Act for the change of use of a building in unorganized territory.

    Open OBC Div. C 1.3.1.4. in the code viewer
  • OBC Div. C 1.3.1.5. Conditional Permits

    (1)The chief building official shall not issue a conditional permit for any stage of construction under subsection 8(3) of the Act unless compliance with the following applicable laws has been achieved in respect of the proposed building or construction:

    (a)section 3 of the Building Transit Faster Act, 2020 with respect to the issuance of a permit under that section,

    (b)section 28 of the Conservation Authorities Act with respect to the prohibition of development activities,

    (c)sections 28.1, 28.1.1 and 28.1.2 of the Conservation Authorities Act with respect to a permit issued for the construction of a building or structure or for any change to a building or structure that would increase its size, alter its use or increase the number of dwelling units,

    (d)regulations made by a conservation authority under clause 28(1)(c) of the Conservation Authorities Act as it read immediately before its repeal by section 25 of Schedule 4 to the Building Better Communities and Conserving Watersheds Act, 2017, with respect to permission of the authority for the construction of a building or structure if, in the opinion of the authority, the control of flooding, erosion, dynamic beaches or pollution or the conservation of land may be affected by the development,

    (e)section 17.2 of the Environmental Assessment Act with respect to the approval of the Minister or the Ontario Land Tribunal to proceed with a project,

    (f)subsection 24(3) of the Niagara Escarpment Planning and Development Act,

    (g)subsection 27(9) of the Ontario Heritage Act,

    (h)subsection 30(2) of the Ontario Heritage Act with respect to a consent of the council of a municipality to the alteration or demolition of a building where the council of the municipality has given a notice of intent to designate the building under subsection 29(3) of that Act,

    (i)section 33 of the Ontario Heritage Act with respect to the consent of the council of a municipality for the alteration of property,

    (j)section 34 of the Ontario Heritage Act with respect to the consent of the council of a municipality for the demolition of a building,

    (k)section 34.5 of the Ontario Heritage Act with respect to the consent of the Minister to the alteration or demolition of a designated building,

    (l)subsection 34.7(2) of the Ontario Heritage Act with respect to a consent of the Minister to the alteration or demolition of a building where the Minister has given a notice of intent to designate the building under section 34.6 of that Act,

    (m)by-laws made under section 40.1 of the Ontario Heritage Act,

    (n)section 42 of the Ontario Heritage Act with respect to the permit given by the council of a municipality for the erection, alteration or demolition of a building,

    (o)section 17.4 of the Ontario New Home Warranties Plan Act with respect to the provision of a confirmation by the Registrar for the construction of a residential condominium conversion project.

    (2)For the purposes of issuing a conditional permit under subsection 8(3) of the Act, a person is exempt from the requirement in clause 8(3)(a) of the Act of compliance with by-laws passed under sections 34 and 38 of the Planning Act where,

    (a)a committee of adjustment has made a decision under section 45 of the Planning Act authorizing one or more minor variances from the provisions of any by-laws made under sections 34 and 38 of that Act,

    (b)such minor variance or variances result in the achievement of full compliance with such by-laws, and

    (c)no person informed the committee of adjustment of objections to the minor variances either in writing or in person at the hearing of the application.

    (3)For the purposes of issuing a conditional permit under subsection 8(3) of the Act, a person is exempt from the requirement in clause 8(3)(a) of the Act of compliance with by-laws passed under sections 34 and 38 of the Planning Act where the construction in respect of which the conditional permit is issued is required in order to comply with an order issued under subsection 21(1) of the Fire Protection and Prevention Act, 1997 or under subsection 15.9(4) of the Act.

    (4)A permit issued under subsection 8(3) of the Act shall indicate its conditional nature.

    Open OBC Div. C 1.3.1.5. in the code viewer
  • OBC Div. C 1.3.1.6. Information to be Given to Tarion Warranty Corporation

    (1)This Article prescribes, for the purposes of subsection 8(8.1) of the Act, the information relating to permits issued under section 8 of the Act and the applications for those permits that the chief building official is required to give to Tarion Warranty Corporation and the time within which the information is required to be given.

    (2)The chief building official shall give the following information to Tarion Warranty Corporation with respect to permits issued under section 8 of the Act in respect of the construction of buildings described in Sentence (4),

    (a)the dates the permits are issued and the numbers or other identifying symbols for the permits, and

    (b)the information contained in the application forms submitted in respect of the permits, other than the information contained in the schedules or other attachments to the application forms.

    (3)Despite Sentence (2), the chief building official is not required to give to Tarion Warranty Corporation information which relates to the extension or material alteration or repair of an existing building.

    (4)The buildings referred to in Sentence (2) are any building whose proposed use is classified as a Group C major occupancy and which is not a boarding, lodging or rooming house or a building containing a hotel.

    (5)The chief building official shall give the information described in Sentence (2) within 45 days after the day on which the permits to which the information relates are issued.

    (6)The time period described in Sentence (5) shall not include Saturdays, holidays and all other days when the offices of the principal authority are not open for the transaction of business with the public.

    Open OBC Div. C 1.3.1.6. in the code viewer
  • OBC Div. C 1.3.1.7. Information to be Given to the Fire Chief or Clerk

    (1)This Article applies to buildings,

    (a)constructed using,

    (i)lightweight pre-engineered floor or roof systems containing lightweight elements such as wood I-joists, cold-formed steel joists, wood truss assemblies with metal or wood plates and metal web wood joists, or

    (ii)lightweight floor or roof systems containing solid sawn lumber joist less than 38 mm by 235 mm,

    (b)other than a house, with or without a secondary unit, and

    (c)for which a permit under section 8 of the Act is issued after July 1, 2022.

    (2)The chief building official shall give the following information to the chief of the fire department and the clerk of every municipality that does not have a fire department in respect of buildings described in Sentence (1):

    (a)the dates the permits are issued and the numbers or other identifying symbols for the permits,

    (b)the address of the building, and

    (c)a description of the floor or roof system.

    (3)The chief building official shall give the information described in Sentence (2) within 45 days after the day on which the permits to which the information relates are issued.

    (4)The time period described in Sentence (3) shall not include Saturdays, holidays and all other days when the offices of the principal authority are not open for the transaction of business with the public.

    Open OBC Div. C 1.3.1.7. in the code viewer
  • OBC Div. C 1.3.2.1. Permit Posting

    (1)Where a permit has been issued pursuant to the Act, the person to whom it is issued shall have the permit or a copy of it posted at all times during construction or demolition in a conspicuous place on the property in respect of which the permit was issued.

    Open OBC Div. C 1.3.2.1. in the code viewer
  • OBC Div. C 1.3.2.2. Documentation on Site

    (1)The person in charge of the construction of the building shall keep and maintain on the site of the construction,

    (a)at least one copy of drawings and specifications certified by the chief building official or a person designated by the chief building official to be a copy of those submitted with the application for the permit to construct the building, together with changes that are authorized by the chief building official or a person designated by the chief building official,

    (b)copies of authorizations of the Building Materials Evaluation Commission on the basis of which the permit was issued, and

    (c)copies of rulings of the Minister, made under clause 29(1)(a) or (c) of the Act, on the basis of which the permit was issued.

    Open OBC Div. C 1.3.2.2. in the code viewer
  • OBC Div. C 1.3.3.1. Occupancy Permit — General

    (1)Except as permitted in Sentence 1.3.3.2.(1), a person may occupy or permit to be occupied any building or part of it that has not been fully completed at the date of occupation where the chief building official or a person designated by the chief building official has issued a permit authorizing occupation of the building or part of it prior to its completion in accordance with Sentence (3).

    (2)Sentence (1) does not apply in respect of the occupancy of a building to which Article 1.3.3.4., 1.3.3.5. or 1.3.3.7. applies or a building or part of it to which Article 1.3.3.8. applies.

    (3)The chief building official or a person designated by the chief building official shall issue a permit authorizing occupation of a building, where,

    (a)the structure of the building or part of it is completed to the roof,

    (b)the enclosing walls of the building or part of them are completed to the roof,

    (c)the walls enclosing the space to be occupied are completed, including balcony guards,

    (d)all required fire separations and closures are completed on all storeys to be occupied,

    (e)all required exits are completed, including all fire separations, doors, door hardware, self-closing devices, guards and handrails, from the uppermost floor to be occupied down to grade level and below if an exit connects with lower storeys,

    (f)all shafts including closures are completed to the floor-ceiling assembly above the storey to be occupied and have a temporary fire separation at such assembly,

    (g)measures have been taken to prevent access to parts of the building and site that are incomplete or still under construction,

    (h)floors, halls, lobbies and required means of egress are free of loose materials and other hazards,

    (i)if service rooms should be in operation, required fire separations and closures are completed,

    (j)all building drains, building sewers, water systems, drainage systems and venting systems are complete and tested as operational for the storeys to be occupied,

    (k)required lighting, heating and electrical supply are provided for the suites, rooms and common areas to be occupied,

    (l)required lighting in corridors, stairways and exits is completed and operational up to and including all storeys to be occupied,

    (m)required standpipe, sprinkler and fire alarm systems are complete and operational up to and including all storeys to be occupied, together with required pumper connections for such standpipes and sprinklers,

    (n)required fire extinguishers have been installed on all storeys to be occupied,

    (o)main garbage rooms, chutes and ancillary services are completed to all storeys to be occupied,

    (p)required firefighting access routes have been provided and are accessible, and

    (q)the sewage system has been completed and is operational.

    (4)Where a registered code agency has been appointed to perform the functions described in clause 4.1(4)(b) or (c) of the Act in respect of the construction of the building, the chief building official or a person designated by the chief building official shall issue the permit referred to in Sentence (3) after receipt of a certificate for the occupancy of a building not fully completed issued by the registered code agency in respect of the building.

    (5)Where applicable, the chief building official or a person designated by the chief building official shall not issue a permit authorizing occupation of the building or part of it, unless compliance with section 168.3.1 of the Environmental Protection Act has been achieved.

    Open OBC Div. C 1.3.3.1. in the code viewer
  • OBC Div. C 1.3.4.1. Fire Department Approval

    (1)Subject to Sentence (2), if the council of a municipality assigns specific responsibility for the enforcement of any portion of this Code respecting fire safety matters to an inspector who is the chief of the fire department of the municipality, the chief building official shall not issue a permit to construct a building unless the inspector approves the drawings submitted with the application for the permit as complying with that portion of this Code.

    (2)If a registered code agency has been appointed under clause 4.1(4)(a) or (c) of the Act,

    (a)a municipality shall not assign responsibility under Sentence (1) to the chief of the fire department with respect to a building for which the registered code agency has been appointed, and

    (b)any assignment of responsibility under Sentence (1) with respect to a building for which the registered code agency is appointed shall be cancelled as of the date of the appointment.

    Open OBC Div. C 1.3.4.1. in the code viewer
  • OBC Div. C 1.3.5.1. Prescribed Notices

    (1)This Article sets out the notices that are required under section 10.2 of the Act.

    (2)The person to whom a permit under section 8 of the Act is issued shall notify the chief building official or, where a registered code agency is appointed under the Act in respect of the construction to which the notice relates, the registered code agency of,

    (a)readiness to construct footings,

    (b)substantial completion of footings and foundations prior to commencement of backfilling,

    (c)substantial completion of structural framing and ductwork and piping for heating and air-conditioning systems, if the building is within the scope of Part 9 of Division B,

    (d)substantial completion of structural framing and roughing-in of heating, ventilation, air-conditioning and air-contaminant extraction equipment, if the building is not a building to which Clause (c) applies,

    (e)substantial completion of insulation and vapour barriers,

    (f)substantial completion of air barrier systems,

    (g)substantial completion of all required fire separations and closures and all fire protection systems including standpipe, sprinkler, fire alarm and emergency lighting systems,

    (h)substantial completion of fire access routes,

    (i)readiness for inspection and testing of,

    (i)building sewers and building drains,

    (ii)water service pipes,

    (iii)fire service mains,

    (iv)drainage systems and venting systems,

    (v)the water distribution system, and

    (vi)plumbing fixtures and plumbing appliances,

    (j)readiness for inspection of suction and gravity outlets, covers and suction piping serving outlets of an outdoor pool described in Clause 1.3.1.1.(1)(j) of Division A, a public pool or a public spa,

    (k)substantial completion of the circulation / recirculation system of an outdoor pool described in Clause 1.3.1.1.(1)(j) of Division A, a public pool or public spa and substantial completion of the pool before it is first filled with water,

    (l)readiness to construct the sewage system,

    (m)substantial completion of the installation of the sewage system before the commencement of backfilling,

    (n)substantial completion of installation of plumbing not located in a structure, before the commencement of backfilling,

    (o)completion of construction and installation of components required to permit the issue of an occupancy permit under Sentence 1.3.3.1.(3) or to permit occupancy under Sentence 1.3.3.2.(1), if the building or part of the building to be occupied is not fully completed, and

    (p)completion of construction and installation of components required to permit the issue of an occupancy permit under Sentence 1.3.3.4.(4), 1.3.3.5.(3) or 1.3.3.7.(8).

    (q)completion of construction and installation of components required to permit the issue of an occupancy permit under Sentence 1.3.3.8.(2).

    Open OBC Div. C 1.3.5.1. in the code viewer
  • OBC Div. C 1.3.5.2. Additional Notices

    (1)A by-law, resolution or regulation made by a principal authority under clause 7(1)(e) of the Act may require that notice of one or more of the following stages of construction be given by the person to whom a permit is issued under section 8 of the Act:

    (a)commencement of construction of the building,

    (b)substantial completion of structural framing for each storey, if the building is a type of building that is within the scope of Division B, other than Part 9,

    (c)commencement of construction of,

    (i)masonry fireplaces and masonry chimneys,

    (ii)factory-built fireplaces and allied chimneys, or

    (iii)stoves, ranges, space heaters and add-on furnaces using solid fuels and allied chimneys,

    (d)substantial completion of interior finishes,

    (e)substantial completion of heating, ventilating, air-conditioning and air-contaminant extraction equipment,

    (f)substantial completion of exterior cladding,

    (g)substantial completion of site grading,

    (h)substantial completion of the pool deck and dressing rooms for a public pool or public spa and readiness for inspection of the emergency stop system for a public pool or public spa,

    (i)completion and availability of drawings of the building as constructed, and

    (j)completion of a building for which an occupancy permit is required under Article 1.3.3.4., 1.3.3.5. or 1.3.3.7. or 1.3.3.8.

    Open OBC Div. C 1.3.5.2. in the code viewer
  • OBC Div. C 1.3.5.3. Prescribed Inspections

    (1)Except as provided in Sentence (2), an inspector or registered code agency, as the case may be, shall, not later than two days after receipt of a notice given under Sentence 1.3.5.1.(2), undertake a site inspection of the building to which the notice relates.

    (2)Where a notice given under Sentence 1.3.5.1.(2) relates to matters described in Clause 1.3.5.1.(2)(l) or (m), an inspector or registered code agency, as the case may be, shall, not later than five days after receipt of the notice, undertake a site inspection of the sewage system to which the notice relates.

    (2.1)Where a notice given under Sentence 1.3.5.1.(2) relates to matters described in Clause 1.3.5.1.(2)(q), an inspector or registered code agency, as the case may be, shall, not later than ten days after receipt of the notice, undertake a site inspection of the building to which the notice relates.

    (3)When undertaking an inspection required under Sentence (1), (2) or (2.1), the inspector or registered code agency, as the case may be, may consider reports concerning whether the building or a part of the building complies with the Act or this Code.

    (4)For greater certainty, when undertaking an inspection required under Sentence (1), (2) or (2.1), the inspector or registered code agency, as the case may be, may choose to not attend at the physical site of the building and may instead undertake the inspection using other means.

    (5)The time periods referred to in Sentences (1), (2) and (2.1) shall begin on the day following the day on which the notice is given.

    (6)The time periods referred to in Sentences (1), (2) and (2.1) shall not include Saturdays, holidays and all other days when the offices of the principal authority are not open for the transaction of business with the public.

    Open OBC Div. C 1.3.5.3. in the code viewer
  • OBC Div. C 1.3.6.1. Application

    (1)Where a by-law, resolution or regulation has been made by a principal authority under clause 7(1)(g) of the Act, the chief building official may require that as constructed plans for the whole of, or any part or system of, a building or any class of buildings be provided by the persons responsible for the construction.

    Open OBC Div. C 1.3.6.1. in the code viewer
  • OBC Div. C 1.5.1.1. General

    (1)The director and employees in the Ministry of Municipal Affairs and Housing who work under the supervision of the director and are specified by the director are designated for the purposes of the enforcement of the Act and this Code in relation to the qualifications of,

    (a)chief building officials,

    (b)inspectors,

    (c)registered code agencies,

    (d)persons engaging in the activities described in subsection 15.11(5) of the Act, and

    (e)persons engaged in the business of constructing on site, installing, repairing, servicing, cleaning or emptying sewage systems.

    (2)The director may, for the purposes set out in Sentence (1), exercise the following powers under the Act of a chief building official:

    (a)certify for the purposes of subsection 37(2) of the Act statements as to any matter of record in the office of the director, and

    (b)apply for an order under section 38 of the Act.

    (3)The employees in the Ministry of Municipal Affairs and Housing designated by the director may, for the purposes set out in Sentence (1), exercise the following powers under the Act of an inspector:

    (a)subject to section 16 of the Act, exercise the powers of entry for inspection purposes in subsection 12(1) of the Act, and

    (b)exercise the powers of an inspector under section 18 of the Act.

    (4)Sections 15.23 and 19 of the Act apply to the exercise of powers under this Article by the director and employees in the Ministry of Municipal Affairs and Housing designated by the director.

    Open OBC Div. C 1.5.1.1. in the code viewer
  • OBC Div. C 1.6.1.1. General

    (1)The director is prescribed for the purposes of section 38.1 of the Act.

    Open OBC Div. C 1.6.1.1. in the code viewer
  • OBC Div. C 1.7.1.1. General

    (1)The boards of health and conservation authorities listed in Column 1 of Table 1.7.1.1. are prescribed, for the purposes of subsection 3.1(1) of the Act, as the boards of health and conservation authorities that are responsible for the enforcement of the provisions of the Act and this Code related to sewage systems in the municipalities and territory without municipal organization prescribed in Column 2 of Table 1.7.1.1.

    Open OBC Div. C 1.7.1.1. in the code viewer
  • OBC Div. C 1.8.1.1. Language Used on Required Signs

    (1)All required signs in this Code shall be displayed in the English language or in the English and French languages, including operational material on all life safety equipment and devices.

    Open OBC Div. C 1.8.1.1. in the code viewer
  • OBC Div. C 1.9.1.1. Annual Report

    (1)The report referred to in subsection 7(4) of the Act shall contain the following information in respect of fees authorized under clause 7(1)(c) of the Act:

    (a)total fees collected in the 12-month period ending no earlier than three months before the release of the report,

    (b)the direct and indirect costs of delivering services related to the administration and enforcement of the Act in the area of jurisdiction of the principal authority in the 12-month period referred to in Clause (a),

    (c)a breakdown of the costs described in Clause (b) into at least the following categories:

    (i)direct costs of administration and enforcement of the Act, including the review of applications for permits and inspection of buildings, and

    (ii)indirect costs of administration and enforcement of the Act, including support and overhead costs, and

    (d)if a reserve fund has been established for any purpose relating to the administration or enforcement of the Act, the amount of the fund at the end of the 12-month period referred to in Clause (a).

    (2)The principal authority shall give notice of the preparation of a report under subsection 7(4) of the Act to every person and organization that has requested that the principal authority provide the person or organization with such notice and has provided an address for the notice.

    Open OBC Div. C 1.9.1.1. in the code viewer
  • OBC Div. C 1.9.1.2. Change of Fees

    (1)Before passing a by-law or resolution or making a regulation under clause 7(1)(c) of the Act to introduce or change a fee imposed for applications for a permit, for the issuance of a permit or for a maintenance inspection, a principal authority shall,

    (a)hold the public meeting required under subsection 7(6) of the Act,

    (b)ensure that a minimum of 21 days notice of the public meeting is given in accordance with Clause (c), including giving 21 days notice to every person and organization that has, within five years before the day of the public meeting, requested that the principal authority provide the person or organization with such notice and has provided an address for the notice,

    (c)ensure that the notice under Clause (b),

    (i)sets out the intention of the principal authority to pass the by-law or resolution or make a regulation under section 7 of the Act and whether the by-law, resolution or regulation would impose any fee that was not in effect on the day the notice is given or would change any fee that was in force on the day the notice is given,

    (ii)is sent by regular mail to the last address provided by the person or organization that requested the notice in accordance with Clause (b), and

    (iii)sets out the information described in Clause (d) or states that the information will be made available at no cost to any member of the public upon request, and

    (d)make the following information available to the public:

    (i)an estimate of the costs of administering and enforcing the Act by the principal authority,

    (ii)the amount of the fee or of the change to the existing fee, and

    (iii)the rationale for imposing or changing the fee.

    Open OBC Div. C 1.9.1.2. in the code viewer
  • OBC Div. C 1.11.1.1. Scope

    (1)This Section applies to houses that,

    (a)have not more than one dwelling unit,

    (b)are 37 m² or less in building area, and

    (c)are to be,

    (i)partially constructed in one municipality and moved to be installed at a location in another municipality without having been previously occupied, or

    (ii)partially constructed at one location and moved to be installed at a location that is not yet known without having been previously occupied.

    (2)Except as provided in this Section, the requirements in this Part apply to houses described in Sentence (1).

    Open OBC Div. C 1.11.1.1. in the code viewer
  • OBC Div. C 1.11.1.2. Permits

    (1)Provided the conditions described in Sentence (2) are complied with, if an applicant for a permit under section 8 of the Act makes an application to the chief building official of the municipality in which a house is to be partially constructed but not installed, the applicant is exempt from demonstrating compliance with,

    (a)either,

    (i)if the application is for a permit described in subsection 8(1) of the Act, clause 8(2)(a) of the Act but only with respect to demonstrating compliance with applicable law, or

    (ii)if the application is for a conditional permit described in subsection 8(3) of the Act, clause 8(3)(a) of the Act, and

    (b)requirements of this Code related to site installation of the house.

    (2)For a permit applicant to be exempt from the provisions described in Sentence (1), the following conditions must be satisfied:

    1. If the site the house is intended to be installed on is known by the permit applicant,

    (i) the permit application must state the address or location of the site,

    (ii) the permit application must include such information about the anticipated site installation that is necessary to design the house, and

    (iii) the proposed construction must comply with the location-dependent requirements of this Code that are applicable to a house that is constructed at that address or location.

    2. If the site the house is intended to be installed on is not known by the permit applicant,

    (i) the permit application must include a declaration of assumptions related to the location of the house that have been used in the design of the house,

    (ii) the permit application must include such information about the anticipated site installation that is necessary to design the house, and

    (iii) the proposed construction must comply with the location-dependent requirements of this Code that are applicable to a house that is constructed at a location that has the characteristics set out in the declaration.

    (3)For the purposes of paragraphs 1 and 2 of Sentence (2), “location-dependent requirements” include, but are not limited to, provisions related to climatic loads, seismic loads, temperature based requirements, limiting distance and exposing building face, soil gas control and firefighting access.

    (4)An applicant for a permit described in Sentence (1) shall provide the following to a purchaser of a house constructed in accordance with a permit described in Sentence (1):

    (1) all plans, specifications, documents and other information submitted or received by the person described in Sentence (1) in respect of the permit described in Sentence (1), including any as-constructed plans and any declaration of assumptions described in subparagraph 2.i. of Sentence (2), and

    (2) all letters of compliance described in Sentence 1.11.1.3.(3) and all documents and other information received by the person described in Sentence (1) in respect of all inspections completed by an inspector or registered code agency, as the case may be.

    (5)No person shall install a house at a site in a municipality unless a permit under section 8 of the Act has been issued therefor by the chief building official of that municipality.

    (6)The chief building official of the municipality in which the house is to be installed shall issue the permit described in Sentence (5) if the applicant,

    (a)demonstrates the proposed construction complies with the applicable provisions described in Clauses (1)(a) and

    (b)

    (b) demonstrates compliance with the other requirements of section 8 of the Act, and

    (c)submits all plans, specifications, documents and other information described in Sentence (4) that the applicant has been provided.

    (7)For the purposes of an application for a permit described in Sentence (5), the time periods described in Sentences 1.3.1.3.(1) and (3) and Clause 1.3.1.3.(6)(b) shall begin on the later of,

    (a)the date the permit described in Sentence (1) is issued, or

    (b)the date described in Sentence 1.3.1.3.(7).

    Open OBC Div. C 1.11.1.2. in the code viewer
  • OBC Div. C 1.11.1.3. Inspections

    (1)Where a permit is applied for as described in Sentence 1.11.1.2.(1) or (5), the person to whom a permit under section 8 of the Act is issued shall give notice as described in Articles 1.3.5.1. and 1.3.5.2. to the chief building official or registered code agency, as the case may be, of the municipality who issued the permit in respect of the construction to which the notice relates.

    (2)Where a permit is applied for as described in Sentence 1.11.1.2.(5), the person to whom a permit under section 8 of the Act is issued shall provide the chief building official of the municipality in which the house is to be installed,

    (a)any additional letters of compliance, documents or other information related to inspections completed by an inspector or registered code agency, as the case may be, of the municipality in which the house was partially constructed that was not provided when the permit was applied for, or

    (b)confirmation that no additional letters of compliance, documents or other information have been provided to the person.

    (3)The chief building official of the municipality in which a house was partially constructed but not installed shall provide the person to whom a permit was issued with a letter of compliance that confirms,

    (a)which prescribed notices described in Sentence 1.3.5.1.(2) were received by the chief building official or registered code agency, as the case may be,

    (b)that inspections described in Sentence 1.3.5.3.(1) were undertaken in respect of the construction to which the notices relate, and

    (c)that no contraventions of the Act or this Code were found or that remedial steps were carried out to resolve any contraventions that were found.

    Open OBC Div. C 1.11.1.3. in the code viewer
  • OBC Div. C 1.12.1.1. Certification and Compliance

    (1)Except as provided in Sentence (2), a manufactured building or a manufactured part of a building within the scope of Part 3 is deemed to comply with this Code if it is certified in accordance with CSA A277, “Procedure for Certification of Prefabricated Buildings, Modules, and Panels.”

    (2)The requirements of this Code shall apply to,

    (a)building components designed and constructed outside the place of manufacture, and

    (b)site installation of such buildings.

    Open OBC Div. C 1.12.1.1. in the code viewer