Values this chapter turns on
- minimum motion sensor timer in public corridors
- 15 min
- minimum motion sensor timer in public corridors
- max total tent area exempt from a permit
- 60 m²
- max total tent area exempt from a permit
- tent area needing an engineer for framing
- 225 m²
- tent area needing an engineer for framing
- building age before Part 11 renovation rules
- 5 years
- building age before Part 11 renovation rules
The last section of the syllabus is a mix: the Part 11 compliance alternatives used in renovations, the Part 12 rule on motion sensors for lighting, and the Division C administrative rules a fire protection inspector meets every day, from who must design certain fire-related items to the notices, occupancy permits and alternative solutions.
Renovation compliance alternatives
Part 11 offers compliance alternatives in Tables 11.5.1.1.-A to F that may replace specific requirements when renovating (OBC Div. B 11.5.1.1.OBC Div. B 11.5.1.1. Compliance Alternatives(1) A compliance alternative shown in Table 11.5.1.1.-A, 11.5.1.1.-B, 11.5.1.1.-C, 11.5.1.1.-D/E or 11.5.1.1.-F may be substituted for a requirement contained in Part 3, 4, 6 or 8 where the chief building official is satisfied that compliance with the requirement is impracticable because, (a) of structural or…). The condition depends on which Part the requirement comes from:
| Requirement from | Condition to use a compliance alternative |
|---|---|
| Part 3, 4, 6 or 8 | the chief building official is satisfied compliance is impracticable because of structural or construction difficulties, or harm to a heritage building |
| Part 9 or 12 | no impracticability test |
Part 11 applies to buildings at least five years old (Div. A 1.3.3.3B.). A compliance alternative is a pre-approved substitute listed in the code. It is not an alternative solution, which needs its own documentation under Division C Part 2.
Motion sensors (Part 12)
Part 12 covers resource conservation and environmental integrity (12.1.1.2.OBC Div. B 12.1.1.2. Application(1) This Part applies to resource conservation and environmental integrity in the design and construction of buildings.). Its fire-relevant rule: lighting that provides minimum code illumination may be on motion sensors, except (12.2.4.1.OBC Div. B 12.2.4.1. Motion Sensors(1) Lighting installed to provide the minimum illumination levels required by this Code may be controlled by motion sensors except where the lighting (a) is installed in an exit, (b) is installed in a corridor serving patients or residents in a Group B, Division 2 or Division 3 occupancy, or (c) is required to conform…):
- lighting in an exit,
- lighting in a corridor serving patients or residents in B2 or B3,
- aisle lighting in theatres and similar spaces under 3.2.7.1.(10),
- any emergency lighting.
In public corridors and public access-to-exit corridors, sensors need fail-safe controllers and timers of at least 15 minutes.
Design by architects and engineers
The syllabus covers Div. C 1.2.1.2. except Sentence (1) (foundations). Fire-related design items (OBC Div. C 1.2.1.2.OBC Div. C 1.2.1.2. Design by Architect or Professional Engineer(1) A foundation of a building shall be designed by a professional engineer where, (a) the foundation is to be constructed below the level of the footings of an adjacent building and within the angle of repose of the soil, as drawn from the bottom of the footings, or (b) underpinning of a foundation is to be…):
| Item | Designer |
|---|---|
| Sprinkler protected glazed wall assembly (3.1.8.20.) | professional engineer |
| Shelf and rack storage system (3.16.) | professional engineer |
| Time-based egress analysis for rack storage | architect or engineer, or both |
| Tent framing and anchorage over 225 m² | professional engineer |
| Projecting sign over 115 kg, roof sign face over 10 m², sign on a parapet | architect or engineer, or both |
Permits, occupancy and notices
Division C applies to all buildings and is administered under the Act (1.1.1.1.OBC Div. C 1.1.1.1. Application(1) This Part applies to all buildings covered in this Code. (See Article 1.1.1.1. of Division A.), 1.1.1.2.OBC Div. C 1.1.1.2. Conformance with Administrative Requirements(1) This Code shall be administered in conformance with the Act.).
Permit exemptions (1.3.1.1.OBC Div. C 1.3.1.1. Requirement for Permits(1) A person is exempt from the requirement to obtain a permit under section 8 of the Act, (a) for the demolition of a farm building located on a farm, (b) subject to Sentence (2), for the construction or demolition of a building in territory without municipal organization, or (c) for the construction of a Class 1…) include demolishing a farm building on a farm, small tents (max 60 m² total, not attached, more than 3 m from other structures), sheds up to 15 m² without plumbing, and demountable stages outside 3.17. Occupants must have left before demolition starts unless their safety is unaffected.
Change of use permits under section 10 of the Act (1.3.1.4.OBC Div. C 1.3.1.4. Permits Under Section 10 of the Act(1) Except as provided in Sentence (2), the following changes in use of a building or part of a building constitute an increase in hazard for the purposes of section 10 of the Act and require a permit under section 10 of the Act: (a) a change of the major occupancy of all or part of a building that is designated with…) are needed for listed increases in hazard: a "Y" change in Table 1.3.1.4., splitting a Group C suite, A2 or A4 to gaming, farm building to a non-farm occupancy or to G1, to a post-disaster building or retirement home, or an unknown previous use. No section 10 permit is needed if a section 8 permit already covers the construction.
The permit (or a copy) is posted conspicuously during the work, and the permitted drawings, authorizations and rulings are kept on site (1.3.2.1.OBC Div. C 1.3.2.1. Permit Posting(1) Where a permit has been issued pursuant to the Act, the person to whom it is issued shall have the permit or a copy of it posted at all times during construction or demolition in a conspicuous place on the property in respect of which the permit was issued., 1.3.2.2.OBC Div. C 1.3.2.2. Documentation on Site(1) The person in charge of the construction of the building shall keep and maintain on the site of the construction, (a) at least one copy of drawings and specifications certified by the chief building official or a person designated by the chief building official to be a copy of those submitted with the application…).
Occupancy before completion (1.3.3.1.OBC Div. C 1.3.3.1. Occupancy Permit — General(1) Except as permitted in Sentence 1.3.3.2.(1), a person may occupy or permit to be occupied any building or part of it that has not been fully completed at the date of occupation where the chief building official or a person designated by the chief building official has issued a permit authorizing occupation of the…) needs a permit. Fire-related conditions include: fire separations and closures complete on occupied storeys; exits complete from the top occupied floor to grade; shafts complete with a temporary separation above; service room separations done; corridor and exit lighting working; standpipe, sprinkler and fire alarm systems operational up to the occupied storeys with pumper connections; extinguishers installed; and firefighting access routes accessible. Small residential buildings have their own lists (1.3.3.2., 1.3.3.4.), mid-rise wood buildings under 3.2.2.51. or 3.2.2.60. a stricter one requiring completion throughout (1.3.3.5.OBC Div. C 1.3.3.5. Occupancy Permit — Buildings Within the Scope of Article 3.2.2.51. or 3.2.2.60.(1) No person shall occupy or permit to be occupied a building within the scope of Article 3.2.2.51. or 3.2.2.60. of Division B, or part of it, unless the chief building official or a person designated by the chief building official has issued a permit authorizing occupation of the building or part of it in accordance…), and super tall buildings their own rules (1.3.3.7.OBC Div. C 1.3.3.7. Occupancy Permit — Super Tall Buildings(1) This Article applies to a building, (a) that is 65 or more storeys in building height or more than 250 m in height, and (b) for which the applicant for the permit has provided notice in accordance with Sentence (6) to the chief building official that they intend to occupy or permit the building or part of the…).
Prescribed notices (1.3.5.1.OBC Div. C 1.3.5.1. Prescribed Notices(1) This Article sets out the notices that are required under section 10.2 of the Act. (2) The person to whom a permit under section 8 of the Act is issued shall notify the chief building official or, where a registered code agency is appointed under the Act in respect of the construction to which the notice relates…) for fire protection: substantial completion of all fire separations, closures and fire protection systems (standpipe, sprinkler, fire alarm, emergency lighting), of fire access routes, and readiness to test fire service mains. As-constructed plans may be demanded where a by-law allows (1.3.6.1.OBC Div. C 1.3.6.1. Application(1) Where a by-law, resolution or regulation has been made by a principal authority under clause 7(1)(g) of the Act, the chief building official may require that as constructed plans for the whole of, or any part or system of, a building or any class of buildings be provided by the persons responsible for the…).
Alternative solutions and rulings
A person proposing an alternative solutionOBC Div. A 1.4.1.2.(1) Alternative solutionAlternative solution means a substitute for an acceptable solution. gives the chief building official or registered code agency documentation identifying the applicable objectives, functional statements and acceptable solutions and showing, by past performance, tests or evaluation, that the required performance level is met, including assumptions and maintenance needs (OBC Div. C 2.1.1.1.OBC Div. C 2.1.1.1. Documentation(1) The person proposing the use of an alternative solution shall provide documentation to the chief building official or registered code agency that, (a) identifies applicable objectives, functional statements and acceptable solutions, and (b) establishes on the basis of past performance, tests described in Article…). Where no test method exists, tests simulate or exceed service conditions or compare against an accepted product (2.1.1.2.OBC Div. C 2.1.1.2. Tests(1) Where no published test method to establish the suitability of an alternative solution proposed under Article 2.1.1.1. exists, then the tests used for the purposes of that Article shall be designed to simulate or exceed anticipated service conditions or shall be designed to compare the performance of the material…).
The Minister may approve an alternative material, system or design by ruling only where it is consistent with a Building Code Commission decision, an approval in the whole of another province or territory, or an NBC or NPC revision approved by the national commission (2.4.2.1.OBC Div. C 2.4.2.1. Criteria(1) Sentence (2) sets out criteria to be followed by the Minister when making a ruling under clause 29(1)(c) of the Act to approve the use of an alternative material, system or building design. (2) The Minister’s approval of the use of an alternative material, system or building design referred to in Sentence (1) may…). Ministerial interpretations are posted on the Building Code website and given in writing on request (2.4.3.1.OBC Div. C 2.4.3.1. Interpretations By Minister(1) Every interpretation issued by the Minister under section 28.1 of the Act shall be made available to the public, (a) by posting the interpretation on the Building Code website, and (b) by providing a written copy of the interpretation on receipt of a request for it.).
Common traps: compliance alternatives (Part 11 tables) versus alternative solutions (Div. C 2.1.); the 60 m² tent permit exemption versus the 225 m² engineering threshold; thinking an occupancy permit needs the whole building finished.
Chapter review
Chapter at a glance
One line per section: the idea to carry into the exam. Then the answers that most often catch candidates out.
- Renovation compliance alternatives
Part 11 offers compliance alternatives in Tables 11.5.1.1.-A to F that may replace specific requirements when renovating.
- Motion sensors (Part 12)
Part 12 covers resource conservation and environmental integrity.
- Design by architects and engineers
The syllabus covers Div. C 1.2.1.2. except Sentence (1) (foundations).
- Permits, occupancy and notices
Division C applies to all buildings and is administered under the Act.
- Alternative solutions and rulings
A person proposing an gives the chief building official or registered code agency documentation identifying the applicable objectives, functional statements and acceptable…
Practice this chapter
Questions on Renovation, motion sensors and Division C administration, in the exam format, every answer explained and cited to its article. Sign in to start; a free account gets the free questions.
Code cited in this chapter
Based on the official 2024 Building Code Compendium on ontario.ca.
© King's Printer for Ontario, 2024. Reproduced with permission.
OBC Div. B 11.5.1.1. Compliance Alternatives
Open OBC Div. B 11.5.1.1. in the code viewer(1)A compliance alternative shown in Table 11.5.1.1.-A, 11.5.1.1.-B, 11.5.1.1.-C, 11.5.1.1.-D/E or 11.5.1.1.-F may be substituted for a requirement contained in Part 3, 4, 6 or 8 where the chief building official is satisfied that compliance with the requirement is impracticable because,
(a)of structural or construction difficulties, or
(b)it is detrimental to the preservation of a heritage building.
(2)A compliance alternative shown in Table 11.5.1.1.-A, 11.5.1.1.-B, 11.5.1.1.-C, 11.5.1.1.-D/E or 11.5.1.1.-F may be substituted for a requirement contained in Part 9 or 12 without satisfying the chief building official that compliance with the requirement is impracticable.
OBC Div. B 12.1.1.2. Application
Open OBC Div. B 12.1.1.2. in the code viewer(1)This Part applies to resource conservation and environmental integrity in the design and construction of buildings.
OBC Div. B 12.2.4.1. Motion Sensors
Open OBC Div. B 12.2.4.1. in the code viewer(1)Lighting installed to provide the minimum illumination levels required by this Code may be controlled by motion sensors except where the lighting
(a)is installed in an exit,
(b)is installed in a corridor serving patients or residents in a Group B, Division 2 or Division 3 occupancy, or
(c)is required to conform to Sentence 3.2.7.1.(10).
(2)Where motion sensors are used to control minimum lighting in a public corridor or corridor providing access to exit for the public, the motion sensors shall be installed with switch controllers equipped for fail-safe operation and illumination timers set for a minimum 15-minute duration.
(3)A motion sensor shall not be used to control emergency lighting.
OBC Div. C 1.2.1.2. Design by Architect or Professional Engineer
Open OBC Div. C 1.2.1.2. in the code viewer(1)A foundation of a building shall be designed by a professional engineer where,
(a)the foundation is to be constructed below the level of the footings of an adjacent building and within the angle of repose of the soil, as drawn from the bottom of the footings, or
(b)underpinning of a foundation is to be undertaken.
(2)A sprinkler protected glazed wall assembly described in Article 3.1.8.20. of Division B shall be designed by a professional engineer.
(3)A shelf and rack storage system described in Section 3.16. of Division B shall be designed by a professional engineer.
(4)The time-based egress analysis for a shelf and rack storage system described in Sentence 3.16.1.7.(7) of Division B shall be prepared or provided by an architect or a professional engineer or a combination of both.
(5)The supporting framing structure and anchorage system for a tent occupying an area greater than 225 m² shall be designed by a professional engineer.
(6)A sign structure attached in any manner to a building shall be designed by an architect or a professional engineer or a combination of both where it is,
(a)a projecting sign that weighs more than 115 kg, or
(b)a roof sign that has any face that is more than 10 m².
(7)A projecting sign attached in any manner to a parapet wall shall be designed by an architect or a professional engineer or a combination of both.
OBC Div. C 1.1.1.1. Application
Open OBC Div. C 1.1.1.1. in the code viewer(1)This Part applies to all buildings covered in this Code. (See Article 1.1.1.1. of Division A.)
OBC Div. C 1.1.1.2. Conformance with Administrative Requirements
Open OBC Div. C 1.1.1.2. in the code viewer(1)This Code shall be administered in conformance with the Act.
OBC Div. C 1.3.1.1. Requirement for Permits
Open OBC Div. C 1.3.1.1. in the code viewer(1)A person is exempt from the requirement to obtain a permit under section 8 of the Act,
(a)for the demolition of a farm building located on a farm,
(b)subject to Sentence (2), for the construction or demolition of a building in territory without municipal organization, or
(c)for the construction of a Class 1 sewage system.
(2)The exemption in Clause (1)(b) from the requirement to obtain a permit does not apply to the construction of a sewage system in territory without municipal organization.
(3)The application for a permit respecting the demolition of a building to which Sentence 1.2.2.3.(1) applies shall include descriptions of the structural design characteristics of the building and the method of demolition of the building.
(4)No person shall commence demolition of a building or any part of a building before the building has been vacated by the occupants except where the safety of the occupants is not affected.
(5)A tent or group of tents is exempt from the requirement to obtain a permit under section 8 of the Act and is exempt from compliance with the Code provided that the tent or group of tents are,
(a)not more than 60 m² in aggregate ground area,
(b)not attached to a building, and
(c)constructed more than 3 m from other structures.
(6)A shed is exempt from the requirement to obtain a permit under section 8 of the Act and is exempt from compliance with this Code, provided that the shed,
(a)is not more than 15 m² in gross area,
(b)is not more than one storey in building height,
(c)is not attached to a building or any other structure,
(d)is used only for storage purposes ancillary to a principal building on the lot, and
(e)does not have plumbing.
(7)A demountable stage or demountable support structure not regulated by Section 3.17. of Division B is exempt from the requirement to obtain a permit under section 8 of the Act and is exempt from compliance with this Code.
OBC Div. C 1.3.1.4. Permits Under Section 10 of the Act
Open OBC Div. C 1.3.1.4. in the code viewer(1)Except as provided in Sentence (2), the following changes in use of a building or part of a building constitute an increase in hazard for the purposes of section 10 of the Act and require a permit under section 10 of the Act:
(a)a change of the major occupancy of all or part of a building that is designated with a “Y” in Table 1.3.1.4. takes place,
(b)a suite of a Group C major occupancy is converted into more than one suite of Group C major occupancy,
(c)a suite or part of a suite of a Group A, Division 2 or a Group A, Division 4 major occupancy is converted to a gaming premises,
(d)a farm building or part of a farm building is changed to another major occupancy other than a Group G major occupancy,
(e)a farm building or part of a farm building is changed to a Group G, Division 1 major occupancy.
(f)a building or part of a building is changed to a post-disaster building,
(g)a building or part of a building is changed to a retirement home, or
(h)the use of a building or part of a building is changed and the previous major occupancy of the building or part of the building cannot be determined.
(2)A person is exempt from the requirement to obtain a permit under section 10 of the Act where the change in use of the building or part of the building will result from proposed construction and a permit under section 8 of the Act has been issued in respect of such construction.
(3)A person is exempt from the requirement to obtain a permit under section 10 of the Act for the change of use of a building in unorganized territory.
Show all 20 articles
OBC Div. C 1.3.2.1. Permit Posting
Open OBC Div. C 1.3.2.1. in the code viewer(1)Where a permit has been issued pursuant to the Act, the person to whom it is issued shall have the permit or a copy of it posted at all times during construction or demolition in a conspicuous place on the property in respect of which the permit was issued.
OBC Div. C 1.3.2.2. Documentation on Site
Open OBC Div. C 1.3.2.2. in the code viewer(1)The person in charge of the construction of the building shall keep and maintain on the site of the construction,
(a)at least one copy of drawings and specifications certified by the chief building official or a person designated by the chief building official to be a copy of those submitted with the application for the permit to construct the building, together with changes that are authorized by the chief building official or a person designated by the chief building official,
(b)copies of authorizations of the Building Materials Evaluation Commission on the basis of which the permit was issued, and
(c)copies of rulings of the Minister, made under clause 29(1)(a) or (c) of the Act, on the basis of which the permit was issued.
OBC Div. C 1.3.3.1. Occupancy Permit — General
Open OBC Div. C 1.3.3.1. in the code viewer(1)Except as permitted in Sentence 1.3.3.2.(1), a person may occupy or permit to be occupied any building or part of it that has not been fully completed at the date of occupation where the chief building official or a person designated by the chief building official has issued a permit authorizing occupation of the building or part of it prior to its completion in accordance with Sentence (3).
(2)Sentence (1) does not apply in respect of the occupancy of a building to which Article 1.3.3.4., 1.3.3.5. or 1.3.3.7. applies or a building or part of it to which Article 1.3.3.8. applies.
(3)The chief building official or a person designated by the chief building official shall issue a permit authorizing occupation of a building, where,
(a)the structure of the building or part of it is completed to the roof,
(b)the enclosing walls of the building or part of them are completed to the roof,
(c)the walls enclosing the space to be occupied are completed, including balcony guards,
(d)all required fire separations and closures are completed on all storeys to be occupied,
(e)all required exits are completed, including all fire separations, doors, door hardware, self-closing devices, guards and handrails, from the uppermost floor to be occupied down to grade level and below if an exit connects with lower storeys,
(f)all shafts including closures are completed to the floor-ceiling assembly above the storey to be occupied and have a temporary fire separation at such assembly,
(g)measures have been taken to prevent access to parts of the building and site that are incomplete or still under construction,
(h)floors, halls, lobbies and required means of egress are free of loose materials and other hazards,
(i)if service rooms should be in operation, required fire separations and closures are completed,
(j)all building drains, building sewers, water systems, drainage systems and venting systems are complete and tested as operational for the storeys to be occupied,
(k)required lighting, heating and electrical supply are provided for the suites, rooms and common areas to be occupied,
(l)required lighting in corridors, stairways and exits is completed and operational up to and including all storeys to be occupied,
(m)required standpipe, sprinkler and fire alarm systems are complete and operational up to and including all storeys to be occupied, together with required pumper connections for such standpipes and sprinklers,
(n)required fire extinguishers have been installed on all storeys to be occupied,
(o)main garbage rooms, chutes and ancillary services are completed to all storeys to be occupied,
(p)required firefighting access routes have been provided and are accessible, and
(q)the sewage system has been completed and is operational.
(4)Where a registered code agency has been appointed to perform the functions described in clause 4.1(4)(b) or (c) of the Act in respect of the construction of the building, the chief building official or a person designated by the chief building official shall issue the permit referred to in Sentence (3) after receipt of a certificate for the occupancy of a building not fully completed issued by the registered code agency in respect of the building.
(5)Where applicable, the chief building official or a person designated by the chief building official shall not issue a permit authorizing occupation of the building or part of it, unless compliance with section 168.3.1 of the Environmental Protection Act has been achieved.
OBC Div. C 1.3.3.5. Occupancy Permit — Buildings Within the Scope of Article 3.2.2.51. or 3.2.2.60.
Open OBC Div. C 1.3.3.5. in the code viewer(1)No person shall occupy or permit to be occupied a building within the scope of Article 3.2.2.51. or 3.2.2.60. of Division B, or part of it, unless the chief building official or a person designated by the chief building official has issued a permit authorizing occupation of the building or part of it in accordance with Sentence (3).
(2)This Article does not apply in respect of the occupancy of an existing building, or part of it, that has been subject to extension or material alteration or repair.
(3)The chief building official or a person designated by the chief building official shall issue a permit authorizing occupation of a building described in Sentence (1), where
(a)the structure of the building is completed to the roof,
(b)the building envelope, including, but not limited to, cladding, roofing, windows, doors, assemblies requiring fire-resistance ratings, closures, insulation, vapour barriers and air barriers, is complete,
(c)the walls enclosing the space to be occupied are completed, including balcony guards,
(d)all required fire separations and closures are completed,
(e)all required exits are completed, including all fire separations, doors, door hardware, self-closing devices, guards and handrails,
(f)all shafts including closures are completed,
(g)measures have been taken to prevent access to parts of the building and site that are incomplete or still under construction,
(h)floors, halls, lobbies and required means of egress are free of loose materials and other hazards,
(i)if service rooms should be in operation, required fire separations and closures are completed,
(j)all building drains, building sewers, water systems, drainage systems and venting systems are complete and tested as operational for the storeys to be occupied,
(k)required lighting, heating and electrical supply are provided for the suites, rooms and common areas to be occupied,
(l)required lighting in corridors, stairways and exits is completed and operational,
(m)required standpipe, sprinkler and fire alarm systems are complete and operational, together with required pumper connections for such standpipes and sprinklers,
(n)required smoke alarms and carbon monoxide alarms are complete and operational,
(o)required fire extinguishers have been installed,
(p)main garbage rooms, chutes and ancillary services are completed to all storeys to be occupied,
(q)required firefighting access routes have been provided and are accessible, and
(r)the sewage system has been completed and is operational.
(4)Where a registered code agency has been appointed to perform the functions described in clause 4.1(4)(b) or (c) of the Act in respect of the construction of a building described in Sentence (1), the chief building official or a person designated by the chief building official shall issue the permit referred to in Sentence (3) after receipt of a certificate for the occupancy of a building described in Sentence 1.3.3.5.(1) of Division C issued by the registered code agency in respect of the building.
OBC Div. C 1.3.3.7. Occupancy Permit — Super Tall Buildings
Open OBC Div. C 1.3.3.7. in the code viewer(1)This Article applies to a building,
(a)that is 65 or more storeys in building height or more than 250 m in height, and
(b)for which the applicant for the permit has provided notice in accordance with Sentence (6) to the chief building official that they intend to occupy or permit the building or part of the building to be occupied in accordance with this Article.
(2)This Article applies to the occupation of a building where the structure and enclosing walls of the building are not completed to the roof.
(3)For greater certainty, once the structure and enclosing walls of the building are completed to the roof, Article 1.3.3.1. applies to the authorization of occupation of the remainder of the building.
(4)This Article does not permit the occupation of exterior balconies, podiums, terraces, platforms and contained open spaces.
(5)This Article does not permit occupation if the means of egress are located on faces of the building where there is overhead lifting of heavy construction materials, elements and equipment.
(6)The notice described in Clause (1)(b) must have been provided to the chief building official at the time the first application for a permit under section 8 of the Act is made in respect of the building.
(7)No person shall occupy or permit to be occupied a building or part of a building described in Sentence (1) unless the chief building official or a person designated by the chief building official has issued a permit authorizing occupation of the building or part of it in accordance with Sentence (8).
(8)The chief building official or a person designated by the chief building official shall issue a permit authorizing occupation of a building where,
(a)the structure of the building or part of it is completed to the floor of the storey that is 10 storeys above the uppermost storey to be occupied, other than parts of the floor-ceiling assemblies that are unable to be completed because of the ongoing construction,
(b)the enclosing walls of the building or part of the enclosing walls are completed to the floor of the storey that is 5 storeys above the uppermost storey to be occupied,
(c)the walls enclosing the space to be occupied are completed, including balcony guards,
(d)all required fire separations and doors, including door hardware and self-closing devices, are completed on all storeys up to the floor of the storey that is 5 storeys above the uppermost storey to be occupied,
(e)all required closures are completed on all storeys up to and including the uppermost storey to be occupied,
(f)all required exits are completed, including all fire separations, doors, door hardware, self-closing devices, guards and handrails, from the uppermost floor to be occupied down to grade level and below if an exit connects with lower storeys,
(g)all shafts, including closures, are completed to the floor-ceiling assembly that is 5 storeys above the uppermost storey to be occupied and have a temporary fire separation at such assembly,
(h)all shafts in the parts of the building that are incomplete or are still under construction are protected against falling objects,
(i)where there is a crane mast inside the building, walls acting as guards shall,
(i)separate the crane mast from the parts of the building to be occupied, and
(ii)be designed and constructed to withstand the loading values specified in Sentence 4.1.5.15.(1) of Division B, where the crane mast or part of the crane mast is located in a storage garage,
(j)the ceiling of the floor-ceiling assembly above the uppermost storey to be occupied is complete and weather-tight and the floor-ceiling assembly is insulated to prevent condensation,
(k)measures have been taken to,
(i)separate the parts of the building to be occupied from the parts of the building and site that are incomplete or still under construction,
(ii)prevent access to parts of the building and site that are incomplete or still under construction, and
(iii)protect occupants and members of the public while construction is ongoing,
(l)floors, halls, lobbies and required means of egress are free of loose materials and other hazards,
(m)if service rooms should be in operation, required fire separations and closures are completed,
(n)all building drains, building sewers, water systems, drainage systems and venting systems are complete and tested as operational for the storeys to be occupied,
(o)required lighting, heating and electrical supply are provided for the suites, rooms and common areas to be occupied,
(p)required lighting in corridors, stairways and exits is completed and operational up to and including all storeys to be occupied,
(q)required ventilation is installed and operational for the floor areas to be occupied,
(r)required sprinkler, fire alarm and smoke control systems, along with required pumper connections for the sprinklers, are complete and operational up to and including the storey to be occupied,
(s)required standpipe systems are installed and operational up to the storey below the uppermost storey for which the structure of the building is complete, including required pumper connections for such standpipe systems,
(t)required fire extinguishers have been installed on all storeys to be occupied and for which the structure of the building is complete,
(u)main garbage rooms, chutes and ancillary services are completed to all storeys to be occupied,
(v)required firefighting access routes have been provided and are accessible,
(w)required elevators for use by firefighters are complete and tested as operational up to and including the storey immediately above the uppermost storey to be occupied,
(x)a covered way is installed and complete over all required means of egress from the building, and all other areas on the property that can be accessed by occupants of the building, that,
(i)has an unobstructed height of at least 2,400 mm,
(ii)has an unobstructed width of at least the width of the means of egress,
(iii)is capable of supporting any loads likely to be encountered as determined by a professional engineer, including snow loads and impact loads from construction,
(iv)has a weather-tight roof,
(v)has partitions with smooth surfaces on the side accessible to occupants,
(vi)has adequate lighting within the covered way, and
(vii)otherwise complies with the requirements in Articles 3.8.1.3., and 3.8.2.2. of Division B, as applicable, and
(y)the requirements set out in Sentences (9) to (14) are complied with.
(9)The person to whom a permit under section 8 of the Act is issued in respect of the building, and such other person as the chief building official determines, shall,
(a)agree in writing with the municipality to assume all risk in occupying or authorizing the occupation of the building or part of it in accordance with this Article and comply with such other conditions as the chief building official considers necessary, including the provision of security, indemnities and evidence of insurance, and
(b)submit to the chief building official,
(i)a plan for phasing of construction and occupancy,
(ii)a site safety plan addressing the means to ensure safety of the occupants and public while construction is ongoing, including,
(A) measures to protect occupants and the public from risks associated with the lifting of heavy construction materials, elements and equipment,
(B) measures for safeguarding occupant wellbeing while construction is ongoing, including the disposal of construction debris, noise, dust, odour, harmful airborne chemicals, non-airborne contaminants, pests and vibrations, including the transfer of vibrations from concrete pumping and pouring to the parts of the building to be occupied, and
(C) measures to address risks, hazards and occupant comfort associated with the proximity of exterior crane masts, concrete pumping pipes and exterior hoists and their tie-back systems,
(iii)a report from a professional engineer that attests,
(A) to the adequacy of the measures to safeguard life, health and property,
(B) that ongoing construction will not adversely impact the structural adequacy of the parts of the building to be occupied, and
(C) that the design of the climbing barriers, fall protection systems and horizontal and vertical safety nets meets the requirements of Sentence (11),
(iv)a report from a third-party professional engineer that has reviewed the adequacy of the measures to safeguard life, health and property, if that review is required by chief building official, and
(v)the report arising from the review conducted in accordance with Sentence (12).
(10)Measures described in Clause (8)(k) shall include,
(a)providing heat, hot water, cold water, gas, electricity, plumbing or other utility services for the parts of the building to be occupied separate from the services that serve the parts of the building that are incomplete or still under construction,
(b)providing access to the parts of the building to be occupied, including access for occupants, vehicles and deliveries, that is separate and independent from access to the parts of the building and site that are incomplete or still under construction,
(c)ensuring that elevators that serve the parts of the building to be occupied are not used for construction,
(d)ensuring that access to the construction area, including any construction staging and loading areas, shall be on a different face of the building than the access to and within the parts of the building to be occupied,
(e)installing temporary or permanent physical barriers to protect the parts of the building to be occupied from falling machinery, equipment, tools, construction materials and any other material or debris, and
(f)installing climbing physical barriers, fall protection and horizontal and vertical safety nets in accordance with Sentence (11).
(11)The climbing physical barriers, fall protection systems and horizontal and vertical safety nets referred to in Clause (10)(f), shall,
(a)in the case of horizontal fall protection systems and safety nets, extend not less than 3 m from the face of the building,
(b)be installed where there is construction on the exterior of the building or a storey that is unenclosed, and
(c)be located immediately below the storey where the construction is located.
(12)Prior to occupancy, the construction of the parts of the building to be occupied shall be reviewed by a professional engineer or an architect in accordance with Article 1.2.2.1.
(13)Where a registered code agency has been appointed to perform the functions described in clause 4.1(4)(b) or (c) of the Act in respect of the construction of the building, the chief building official or a person designated by the chief building official shall issue the permit referred to in Sentence (8) after receipt of a certificate for the occupancy of a building not fully completed issued by the registered code agency in respect of the building.
(14)Where development charges in respect of a building or part of it are payable in accordance with subsection 26.1 (3.1) of the Development Charges Act, 1997, the development charges have been paid in accordance with that section.
OBC Div. C 1.3.5.1. Prescribed Notices
Open OBC Div. C 1.3.5.1. in the code viewer(1)This Article sets out the notices that are required under section 10.2 of the Act.
(2)The person to whom a permit under section 8 of the Act is issued shall notify the chief building official or, where a registered code agency is appointed under the Act in respect of the construction to which the notice relates, the registered code agency of,
(a)readiness to construct footings,
(b)substantial completion of footings and foundations prior to commencement of backfilling,
(c)substantial completion of structural framing and ductwork and piping for heating and air-conditioning systems, if the building is within the scope of Part 9 of Division B,
(d)substantial completion of structural framing and roughing-in of heating, ventilation, air-conditioning and air-contaminant extraction equipment, if the building is not a building to which Clause (c) applies,
(e)substantial completion of insulation and vapour barriers,
(f)substantial completion of air barrier systems,
(g)substantial completion of all required fire separations and closures and all fire protection systems including standpipe, sprinkler, fire alarm and emergency lighting systems,
(h)substantial completion of fire access routes,
(i)readiness for inspection and testing of,
(i)building sewers and building drains,
(ii)water service pipes,
(iii)fire service mains,
(iv)drainage systems and venting systems,
(v)the water distribution system, and
(vi)plumbing fixtures and plumbing appliances,
(j)readiness for inspection of suction and gravity outlets, covers and suction piping serving outlets of an outdoor pool described in Clause 1.3.1.1.(1)(j) of Division A, a public pool or a public spa,
(k)substantial completion of the circulation / recirculation system of an outdoor pool described in Clause 1.3.1.1.(1)(j) of Division A, a public pool or public spa and substantial completion of the pool before it is first filled with water,
(l)readiness to construct the sewage system,
(m)substantial completion of the installation of the sewage system before the commencement of backfilling,
(n)substantial completion of installation of plumbing not located in a structure, before the commencement of backfilling,
(o)completion of construction and installation of components required to permit the issue of an occupancy permit under Sentence 1.3.3.1.(3) or to permit occupancy under Sentence 1.3.3.2.(1), if the building or part of the building to be occupied is not fully completed, and
(p)completion of construction and installation of components required to permit the issue of an occupancy permit under Sentence 1.3.3.4.(4), 1.3.3.5.(3) or 1.3.3.7.(8).
(q)completion of construction and installation of components required to permit the issue of an occupancy permit under Sentence 1.3.3.8.(2).
OBC Div. C 1.3.6.1. Application
Open OBC Div. C 1.3.6.1. in the code viewer(1)Where a by-law, resolution or regulation has been made by a principal authority under clause 7(1)(g) of the Act, the chief building official may require that as constructed plans for the whole of, or any part or system of, a building or any class of buildings be provided by the persons responsible for the construction.
OBC Div. A 1.4.1.2.(1) Alternative solution
Open OBC Div. A 1.4.1.2.(1) in the code viewerAlternative solution means a substitute for an acceptable solution.
OBC Div. C 2.1.1.1. Documentation
Open OBC Div. C 2.1.1.1. in the code viewer(1)The person proposing the use of an alternative solution shall provide documentation to the chief building official or registered code agency that,
(a)identifies applicable objectives, functional statements and acceptable solutions, and
(b)establishes on the basis of past performance, tests described in Article 2.1.1.2. or other evaluation that the proposed alternative solution will achieve the level of performance required under Article 1.2.1.1. of Division A.
(2)The documentation described in Sentence (1) shall include information about relevant assumptions, limiting or restricting factors, testing procedures, studies or building performance parameters, including any commissioning, operational and maintenance requirements.
OBC Div. C 2.1.1.2. Tests
Open OBC Div. C 2.1.1.2. in the code viewer(1)Where no published test method to establish the suitability of an alternative solution proposed under Article 2.1.1.1. exists, then the tests used for the purposes of that Article shall be designed to simulate or exceed anticipated service conditions or shall be designed to compare the performance of the material or system with a similar material or system that is known to be acceptable.
(2)The results of tests or evaluations based on test standards, other than as described in this Code, may be used for the purposes of Sentence (1), if the alternate test standards provide comparable results.
OBC Div. C 2.4.2.1. Criteria
Open OBC Div. C 2.4.2.1. in the code viewer(1)Sentence (2) sets out criteria to be followed by the Minister when making a ruling under clause 29(1)(c) of the Act to approve the use of an alternative material, system or building design.
(2)The Minister’s approval of the use of an alternative material, system or building design referred to in Sentence (1) may be granted only if the approval is consistent with,
(a)a decision of the Building Code Commission in respect of a dispute described in clause 24(1)(a) of the Act,
(b)an approval of the use of the material, system or building design in the whole of another province or territory in accordance with the law of that province or territory, or
(c)a revision of the NRCC-CONST-56435E 2020, “National Building Code of Canada”, or the NRCC-CONST-56436E 2020, “National Plumbing Code of Canada”, that has been approved by the Canadian Commission on Building and Fire Codes.
OBC Div. C 2.4.3.1. Interpretations By Minister
Open OBC Div. C 2.4.3.1. in the code viewer(1)Every interpretation issued by the Minister under section 28.1 of the Act shall be made available to the public,
(a)by posting the interpretation on the Building Code website, and
(b)by providing a written copy of the interpretation on receipt of a request for it.